3214 S PHILO ST 90064

Certificate Information: 3214 S PHILO ST 90064

Application / Permit
20010-30000-01678
Plan Check / Job No.
B20WL02084
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2 story SFD with attached garage and roof trusses
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 4/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2020 APPLICANT
Assigned to Plan Check Engineer 6/3/2020 TARIK SAOUD
Corrections Issued 6/10/2020 TARIK SAOUD
Quality Review Completed 6/19/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/28/2020 TARIK SAOUD
Plan Check Approved 1/19/2021 TARIK SAOUD
Issued 1/25/2021 APPLICANT
Building Plans Picked Up 1/26/2021 APPLICANT
CofO in Progress 4/20/2022 KEVIN SARGSYAN
Permit Finaled 4/26/2022 DANIEL ORRANTE
CofO Issued 4/26/2022 DANIEL ORRANTE
Permit Finaled 4/26/2022 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 6/11/2020 JOHN KIM
Low Impact Development Cleared 7/30/2020 MARTIN FRAGOSO
Permit Cleared 8/4/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 8/4/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/5/2020 DINAH GARIN
Sewer availability Cleared 8/5/2020 DINAH GARIN
CPC Cleared 8/27/2020 NOAH MCCOY
CPC Cleared 8/27/2020 NOAH MCCOY
CPC Cleared 8/27/2020 NOAH MCCOY
Frnt yard landscape/Water mgmt Cleared 8/27/2020 NOAH MCCOY
Hydrant and Access approval Cleared 8/27/2020 MATTHEW CRAIG
Grading Pre-Inspection Cleared 1/19/2021 TARIK SAOUD

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/4/2021 Approved KEVIN SARGSYAN
Underground Mechanical 3/4/2021 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 3/15/2021 Not Ready for Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 3/16/2021 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 3/16/2021 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 3/18/2021 No Result Entered RONALD WEBER
Excavation/Setback/Form/Re-Bar 3/18/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2021 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 4/12/2021 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 5/3/2021 Approved KEVIN SARGSYAN
Deputy Wood Construction 5/6/2021 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 5/7/2021 Approved KEVIN SARGSYAN
Shower Pan 5/7/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Approved KEVIN SARGSYAN
HVAC-Rough 6/16/2021 Approved KEVIN SARGSYAN
HVAC-Rough 6/17/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/28/2021 Partial Approval JACK MATTILLO
Green Building Rough 6/28/2021 Partial Inspection JACK MATTILLO
MERV13>=Rough 6/28/2021 Not Ready for Inspection JACK MATTILLO
Verify Sprinkler Sign Off 6/28/2021 Not Ready for Inspection JACK MATTILLO
Drywall Nailing 8/19/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Interior/Exterior Lathing 8/19/2021 Not Ready for Inspection SHAVONNE ESPINOZA
Interior/Exterior Lathing 8/25/2021 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/31/2021 No Access for Inspection KEVIN SARGSYAN
Insulation 9/2/2021 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 9/2/2021 Partial Approval KEVIN SARGSYAN
Insulation 9/3/2021 Approved KEVIN SARGSYAN
Drywall Nailing 9/10/2021 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 9/14/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 9/15/2021 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 12/3/2021 Conditional Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 12/6/2021 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Final 12/10/2021 No Access for Inspection EVAN COOPER
ELECTRICAL-Final 12/16/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 12/29/2021 No Access for Inspection KEVIN SARGSYAN
HVAC-Final 1/5/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 1/7/2022 No Access for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 1/18/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 1/18/2022 Approved KEVIN SARGSYAN
Green Building Rough 1/18/2022 Approved KEVIN SARGSYAN
HVAC-Final 1/18/2022 Corrections Issued KEVIN SARGSYAN
MERV13>=Final 1/18/2022 Corrections Issued KEVIN SARGSYAN
MERV13>=Rough 1/18/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 1/18/2022 SGSOV Not Ready KEVIN SARGSYAN
Service/Power Release 1/18/2022 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 1/18/2022 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 1/18/2022 Approved KEVIN SARGSYAN
HVAC-Final 1/31/2022 No Access for Inspection KEVIN SARGSYAN
HVAC-Final 2/11/2022 Partial Approval OGANES TARAKHCHYAN
HVAC-Final 2/18/2022 Approved OGANES TARAKHCHYAN
MERV13>=Final 2/18/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Service/Power Release 2/18/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 2/28/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 3/2/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Not Ready KEVIN SARGSYAN
Final 4/15/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 4/15/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 4/15/2022 Approved KEVIN SARGSYAN
Final 4/19/2022 Corrections Issued KEVIN SARGSYAN
Final 4/20/2022 OK to Issue CofO KEVIN SARGSYAN
Gas Test 4/20/2022 Approved KEVIN SARGSYAN