12338 W MARSHALL ST 90230

Certificate Information: 12338 W MARSHALL ST 90230

Application / Permit
20010-30000-01544
Plan Check / Job No.
B20WL02021
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
new detached two story ADU with atached storage shed
Permit Issued
Issued on 12/30/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2020 APPLICANT
Assigned to Plan Check Engineer 5/28/2020 TARIK SAOUD
Corrections Issued 6/8/2020 TARIK SAOUD
Quality Review Completed 6/18/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 8/21/2020 TARIK SAOUD
Plan Check Approved 11/23/2020 TARIK SAOUD
Building Plans Picked Up 11/23/2020 APPLICANT
Issued 12/30/2020 APPLICANT
CofO in Progress 1/18/2022 ENRIQUE MIRELES
CofO Issued 1/29/2022 DANIEL ORRANTE
Permit Finaled 1/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/9/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 7/14/2020 ANTHONY MAINEZ
Sewer availability Cleared 7/14/2020 ANTHONY MAINEZ
Hydrant and Access approval Cleared 9/10/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/20/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/18/2020 ANTHONY MAINEZ

Contact Information

Contractor Quality First Builders Inc; Lic. No.: 990316-B 5530 CORBIN AVE 345      TARZANA, CA 91356
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/17/2021 Not Ready for Inspection PIERRE VEGA
Sewer 5/17/2021 Approved PIERRE VEGA
Underground Mechanical 5/17/2021 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 6/1/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 6/4/2021 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 6/9/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 6/23/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 6/23/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Approved ENRIQUE MIRELES
Deputy Wood Construction 7/20/2021 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/23/2021 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/23/2021 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 7/23/2021 Approved ENRIQUE MIRELES
Structural Steel Frame 7/23/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 7/23/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 7/27/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 7/27/2021 Approved ENRIQUE MIRELES
Structural Steel Frame 7/27/2021 Approved ENRIQUE MIRELES
Green Building Final 8/6/2021 Not Ready for Inspection ENRIQUE MIRELES
Insulation 8/6/2021 Approved ENRIQUE MIRELES
Drywall Nailing 8/13/2021 Approved ENRIQUE MIRELES
Green Building Final 8/18/2021 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 8/18/2021 Approved ENRIQUE MIRELES
Shower Pan 8/20/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 8/24/2021 Corrections Issued SHAVONNE ESPINOZA
Green Building Final 8/25/2021 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 8/25/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Not Ready ENRIQUE MIRELES
Service/Power Release 8/25/2021 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 8/25/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 1/12/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 1/12/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 1/12/2022 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 1/12/2022 Approved ENRIQUE MIRELES
Smoke Detectors 1/12/2022 Approved ENRIQUE MIRELES
Final 1/18/2022 OK to Issue CofO ENRIQUE MIRELES