12338 W MARSHALL ST 90230
Certificate Information: 12338 W MARSHALL ST 90230
- Application / Permit
- 20010-30000-01544
- Plan Check / Job No.
- B20WL02021
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new detached two story ADU with atached storage shed
- Permit Issued
- Issued on 12/30/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | TARIK SAOUD |
| Corrections Issued | 6/8/2020 | TARIK SAOUD |
| Quality Review Completed | 6/18/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/21/2020 | TARIK SAOUD |
| Plan Check Approved | 11/23/2020 | TARIK SAOUD |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Issued | 12/30/2020 | APPLICANT |
| CofO in Progress | 1/18/2022 | ENRIQUE MIRELES |
| CofO Issued | 1/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/14/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/14/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 9/10/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/20/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/18/2020 | ANTHONY MAINEZ |
Contact Information
| Contractor | Quality First Builders Inc; Lic. No.: 990316-B | 5530 CORBIN AVE 345 TARZANA, CA 91356 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/17/2021 | Not Ready for Inspection | PIERRE VEGA |
| Sewer | 5/17/2021 | Approved | PIERRE VEGA |
| Underground Mechanical | 5/17/2021 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 6/1/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/4/2021 | Approved | ENRIQUE MIRELES |
| Deputy Reinf. Concrete | 6/9/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 6/23/2021 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 7/20/2021 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 7/23/2021 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/23/2021 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 7/23/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/23/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Structural Steel Frame | 7/27/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 8/6/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 8/6/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/13/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 8/18/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/18/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 8/20/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/24/2021 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Final | 8/25/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/25/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/25/2021 | SGSOV Not Ready | ENRIQUE MIRELES |
| Service/Power Release | 8/25/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 8/25/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 1/12/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/12/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 1/12/2022 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/12/2022 | Approved | ENRIQUE MIRELES |
| Final | 1/18/2022 | OK to Issue CofO | ENRIQUE MIRELES |