2701 W 3RD ST 90057
Certificate Information: 2701 W 3RD ST 90057
- Application / Permit
- 20010-30000-01542
- Plan Check / Job No.
- B20WL02009
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- (N) 2-STORY RETAIL STRUCTURE AT AUTOMOTIVE FUELING STATION FACILITY.
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2020 | REZA HAGHIGHAT |
| Corrections Issued | 6/16/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 6/23/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 12/3/2020 | APPLICANT |
| Plan Check Approved | 3/1/2021 | REZA HAGHIGHAT |
| Issued | 8/6/2021 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| Permit Finaled | 2/17/2026 | ERNESTO CORRAL |
| CofO Issued | 2/17/2026 | ERNESTO CORRAL |
| Permit Finaled | 2/17/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Driveway location | Cleared | 8/12/2020 | TAIMOUR TANAVOLI |
| Internal circulation | Cleared | 8/12/2020 | TAIMOUR TANAVOLI |
| Food Service Establishment | Cleared | 8/21/2020 | RAMESHBHAIR PATEL |
| DAS Clearance | Cleared | 8/25/2020 | SOMKIAT SUPANYACHOTSKUL |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2020 | JEANIE LAM |
| Permit | Cleared | 8/27/2020 | JEANIE LAM |
| Sewer availability | Cleared | 8/27/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 8/31/2020 | MATTHEW CRAIG |
| Automotive Use | Cleared | 9/1/2020 | LOUIS ORTEGA |
| Automotive Use | Cleared | 10/7/2020 | LOUIS ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 10/7/2020 | LOUIS ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 10/7/2020 | LOUIS ORTEGA |
| Green Code | Cleared | 12/3/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 2/3/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 2/17/2021 | WALLIE JONG |
| Food establishment approval | Cleared | 3/1/2021 | LACDHS APPROVED |
| Grading Pre-Inspection | Cleared | 3/1/2021 | REZA HAGHIGHAT |
Contact Information
| Architect | Manligas,, Amorsolo Rubio; Lic. No.: C15983 | 13106 CHAPMAN AVENUE APT 4-104 GARDEN GROVE, CA 92840 |
| Contractor | Owner-Builder | , |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
Inspector Information
| NICK DANERI, (213) 202-5615 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Grading Pre-Inspection | 5/31/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 5/31/2022 | Partial Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Pre-Inspection | 8/4/2022 | Corrections Issued | DAVID BURKHEAD |
| Footing/Foundation/Slab | 8/5/2022 | Partial Approval | NICK DANERI |
| METHANE-Barrier | 8/5/2022 | Not Ready for Inspection | NICK DANERI |
| METHANE-Subgrade | 8/5/2022 | Not Ready for Inspection | NICK DANERI |
| Deputy Steel/Welding | 8/9/2022 | Conditional Approval | ERNESTO CORRAL |
| Footing/Foundation/Slab | 8/12/2022 | Partial Approval | NICK DANERI |
| METHANE-Barrier | 8/12/2022 | Partial Approval | NICK DANERI |
| METHANE-Subgrade | 8/12/2022 | Partial Approval | NICK DANERI |
| Deputy Steel/Welding | 8/29/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Wood Construction | 9/12/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 9/13/2022 | Not Ready for Inspection | NICK DANERI |
| METHANE-Rough | 9/13/2022 | Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 9/13/2022 | Not Ready for Inspection | NICK DANERI |
| Wood Frame | 9/13/2022 | Partial Approval | NICK DANERI |
| Deputy Wood Construction | 10/28/2022 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2022 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 11/1/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Wood Construction | 11/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 11/15/2022 | Partial Approval | NICK DANERI |
| Verify Sprinkler Sign Off | 11/15/2022 | Not Ready for Inspection | NICK DANERI |
| Wood Frame | 11/15/2022 | Partial Approval | NICK DANERI |
| Green Building Rough | 11/21/2022 | Partial Inspection | NICK DANERI |
| Insulation | 11/21/2022 | Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 11/21/2022 | Partial Inspection | NICK DANERI |
| Wood Frame | 11/21/2022 | Partial Approval | NICK DANERI |
| Drywall Nailing | 11/28/2022 | Approved | NICK DANERI |
| Interior/Exterior Lathing | 11/28/2022 | Approved | NICK DANERI |
| Footing/Foundation/Slab | 5/22/2023 | Partial Approval | NICK DANERI |
| METHANE-Barrier | 5/22/2023 | Approved | NICK DANERI |
| METHANE-Subgrade | 5/22/2023 | Approved | NICK DANERI |
| Final | 2/10/2025 | Not Ready for Inspection | NICK DANERI |
| Footing/Foundation/Slab | 2/10/2025 | Approved | NICK DANERI |
| Green Building Final | 2/10/2025 | Not Ready for Inspection | NICK DANERI |
| Green Building Rough | 2/10/2025 | Approved | NICK DANERI |
| Reinforced Masonry Frame | 2/10/2025 | Approved | NICK DANERI |
| SGSOV-Seismic Gas S/O Valve | 2/10/2025 | SGSOV Not Ready | NICK DANERI |
| Smoke Detectors | 2/10/2025 | Approved | NICK DANERI |
| Verify Sprinkler Sign Off | 2/10/2025 | Approved | NICK DANERI |
| Wood Frame | 2/10/2025 | Approved | NICK DANERI |
| Final | 12/24/2025 | Corrections Issued | JOEY BUCHANAN |
| Green Building Final | 12/24/2025 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 12/24/2025 | SGSOV Approved | JOEY BUCHANAN |
| Final | 1/30/2026 | Conditional Approval | JOEY BUCHANAN |