4816 S INGLEWOOD BLVD 90230
Certificate Information: 4816 S INGLEWOOD BLVD 90230
- Application / Permit
- 20010-30000-01473
- Plan Check / Job No.
- B20WL01914
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-Story Single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D.
- Permit Issued
- Issued on 8/24/2020
- Issuing Office
- Current Status
- CofO Issued on 7/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2020 | ALFREDO JARA |
| Corrections Issued | 5/26/2020 | ALFREDO JARA |
| Quality Review Completed | 6/5/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 6/9/2020 | APPLICANT |
| Applicant returned to address corrections | 6/30/2020 | ALFREDO JARA |
| Plan Check Approved | 8/14/2020 | ALFREDO JARA |
| Issued | 8/24/2020 | APPLICANT |
| Building Plans Picked Up | 8/24/2020 | APPLICANT |
| CofO in Progress | 6/29/2021 | ENRIQUE MIRELES |
| Permit Finaled | 7/12/2021 | VINCENT COTTON |
| CofO Issued | 7/12/2021 | VINCENT COTTON |
| Permit Finaled | 7/12/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 6/11/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 6/30/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/21/2020 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 7/28/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/28/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2020 | DINAH GARIN |
| Permit | Cleared | 7/29/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/29/2020 | DINAH GARIN |
| Green Code | Cleared | 8/6/2020 | RICHARD GARCIA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/30/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/8/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2020 | Partial Approval | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2020 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Partial Approval | ENRIQUE MIRELES |
| HVAC-Rough | 11/19/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/25/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/9/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/15/2020 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/18/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 12/23/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 12/29/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 1/6/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 1/6/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/12/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/13/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 1/13/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/20/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/22/2021 | No Access for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/27/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 1/27/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 4/6/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 4/20/2021 | Approved | ENRIQUE MIRELES |
| Gas Test | 4/26/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 4/26/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/21/2021 | SGSOV Not Ready | JACK MATTILLO |
| BUILDING-Rough-Frame | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| Final | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| Green Building Final | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| Service/Power Release | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| Smoke Detectors | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| Verify Sprinkler Sign Off | 6/22/2021 | Not Ready for Inspection | JACK MATTILLO |
| BUILDING-Rough-Frame | 6/24/2021 | Approved | ENRIQUE MIRELES |
| Final | 6/24/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 6/24/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/24/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 6/24/2021 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/24/2021 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 6/24/2021 | Approved | ENRIQUE MIRELES |
| Final | 6/29/2021 | OK to Issue CofO | ENRIQUE MIRELES |