17404 W OSBORNE ST 91325

Certificate Information: 17404 W OSBORNE ST 91325

Application / Permit
20010-30000-01378
Plan Check / Job No.
B20WL01807
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
New cabana.
Permit Issued
Issued on 11/25/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 5/12/2020 MANUEL GARCIA
Corrections Issued 5/15/2020 MANUEL GARCIA
Quality Review Completed 5/21/2020 TARIK SAOUD
Applicant returned to address corrections 6/18/2020 MANUEL GARCIA
Applicant returned to address corrections 6/30/2020 MANUEL GARCIA
Green Plans Picked Up 7/8/2020 APPLICANT
Applicant returned to address corrections 9/2/2020 MANUEL GARCIA
Plan Check Approved 11/4/2020 MANUEL GARCIA
Issued 11/25/2020 APPLICANT
Building Plans Picked Up 12/24/2020 APPLICANT
CofO in Progress 6/11/2021 MICHAEL TEMPLE
CofO Issued 6/26/2021 MICHAEL SMITH
Permit Finaled 6/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 6/5/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/10/2020 ADRIAN CASTRO
Green Code Cleared 7/7/2020 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 7/8/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 8/4/2020 KURT CORRAL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/17/2021 Corrections Issued MARK JOHNSON
Excavation/Setback/Form/Re-Bar 3/19/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 4/5/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Approved MARK JOHNSON
Underground Mechanical 4/5/2021 Approved MARK JOHNSON
Verify Sprinkler Sign Off 4/5/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 4/15/2021 Approved MARK JOHNSON
Grounding or Bonding 4/16/2021 Partial Inspection MARK JOHNSON
BUILDING-Rough-Frame 5/12/2021 Approved MARK JOHNSON
Final 5/12/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 5/12/2021 Approved MARK JOHNSON
Green Building Final 5/12/2021 Approved MARK JOHNSON
Green Building Rough 5/12/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved MARK JOHNSON
Service/Power Release 5/12/2021 Not Required MARK JOHNSON
Smoke Detectors 5/12/2021 Approved MARK JOHNSON
Final 6/2/2021 Not Ready for Inspection MARK JOHNSON
Final 6/10/2021 OK to Issue CofO MICHAEL TEMPLE