728 E 112TH ST 90059

Certificate Information: 728 E 112TH ST 90059

Application / Permit
20010-30000-01337
Plan Check / Job No.
B20WL01778
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY TYPE VB ACCESSORY DWELLING UNIT (ADU) WITH ATTACHED 1-CAR GARAGE PER ORDINANCE.
Permit Issued
Issued on 10/13/2020
Issuing Office
Current Status
CofO Issued on 8/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2020 APPLICANT
Assigned to Plan Check Engineer 5/12/2020 SERGIO SILVA
Corrections Issued 6/1/2020 SERGIO SILVA
Quality Review Completed 6/12/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 8/18/2020 APPLICANT
Plan Check Approved 10/5/2020 SERGIO SILVA
Building Plans Picked Up 10/6/2020 APPLICANT
Issued 10/13/2020 APPLICANT
CofO in Progress 5/19/2021 EUGENE CASSIDY
Permit Finaled 8/4/2021 DEROLD HAUFF
CofO Issued 8/4/2021 DEROLD HAUFF
Permit Finaled 8/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2020 JEANIE LAM
Permit Cleared 6/23/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/26/2020 JEANIE LAM
Sewer availability Cleared 6/26/2020 JEANIE LAM
Trees in Parkway Cleared 7/16/2020 JOHN KIM
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/15/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 9/22/2020 CELINA MORENO
Miscellaneous Cleared 10/5/2020 SERGIO SILVA

Contact Information

Contractor De La Rosa Construction; Lic. No.: 855010-B 3684 E PERCY ST      LOS ANGELES, CA 90023
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/20/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/26/2020 Partial Approval EUGENE CASSIDY
Underground Mechanical 10/26/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 10/29/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 11/5/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/19/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 11/19/2020 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 11/19/2020 Approved EUGENE CASSIDY
Deputy Wood Construction 12/2/2020 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 12/3/2020 Approved EUGENE CASSIDY
Gas Test 12/3/2020 Partial Approval EUGENE CASSIDY
HVAC-Rough 12/3/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 12/3/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 12/3/2020 Partial Approval EUGENE CASSIDY
Insulation 12/7/2020 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 12/7/2020 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 12/11/2020 Approved JOHN KLARIN
Rough-Elec/Plmb/HVAC 12/11/2020 Approved JOHN KLARIN
Insulation 12/15/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/15/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/18/2020 Approved DAVID FEILER
Drywall Nailing 12/18/2020 Approved DAVID FEILER
Green Building Rough 12/18/2020 Approved DAVID FEILER
Final 3/31/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 3/31/2021 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Not Ready EUGENE CASSIDY
Service/Power Release 3/31/2021 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 3/31/2021 Approved EUGENE CASSIDY
Final 4/20/2021 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 4/20/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved EUGENE CASSIDY
Service/Power Release 4/20/2021 Not Ready for Inspection EUGENE CASSIDY
Final 5/7/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 5/7/2021 Approved EUGENE CASSIDY
Service/Power Release 5/7/2021 Not Ready for Inspection EUGENE CASSIDY
Final 5/14/2021 Corrections Issued EUGENE CASSIDY
Service/Power Release 5/14/2021 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/19/2021 Approved EUGENE CASSIDY
Final 5/19/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 5/19/2021 Approved EUGENE CASSIDY
PLUMBING-Final 5/19/2021 Approved EUGENE CASSIDY
Service/Power Release 5/19/2021 Approved EUGENE CASSIDY