6016 W COMEY AVE 90034
Certificate Information: 6016 W COMEY AVE 90034
- Application / Permit
- 20010-30000-01179
- Plan Check / Job No.
- B20WL01618
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD with attached garage.
- Permit Issued
- Issued on 8/12/2020
- Issuing Office
- Current Status
- CofO Issued on 11/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2020 | MANUEL GARCIA |
| Corrections Issued | 4/21/2020 | MANUEL GARCIA |
| Quality Review Completed | 5/1/2020 | TARIK SAOUD |
| Green Plans Picked Up | 6/25/2020 | APPLICANT |
| Applicant returned to address corrections | 7/8/2020 | MANUEL GARCIA |
| Plan Check Approved | 8/11/2020 | MANUEL GARCIA |
| Issued | 8/12/2020 | APPLICANT |
| Building Plans Picked Up | 8/12/2020 | APPLICANT |
| CofO in Progress | 11/8/2021 | KENNETH NAGLE |
| Permit Finaled | 11/8/2021 | KENNETH NAGLE |
| CofO Issued | 11/8/2021 | KENNETH NAGLE |
| Permit Finaled | 11/8/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Highway dedication | Cleared | 4/30/2020 | RAYMOND MUGAMBWA |
| Frnt yard landscape/Water mgmt | Cleared | 5/26/2020 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 6/4/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/17/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 6/25/2020 | THOMAS LANG |
| Green Code | Cleared | 6/25/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2020 | RENZ SORIANO |
| Permit | Cleared | 6/26/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 6/26/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 7/16/2020 | NGOC KIEM |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/10/2020 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Approved | EVAN COOPER |
| Deputy Wood Construction | 12/7/2020 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 1/21/2021 | Partial Approval | EVAN COOPER |
| Sewer | 1/21/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2021 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 2/8/2021 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 2/17/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 2/17/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/2/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/3/2021 | Approved | EVAN COOPER |
| Green Building Rough | 3/3/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 3/3/2021 | Partial Approval | EVAN COOPER |
| MERV13>=Rough | 3/3/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/3/2021 | Approved | EVAN COOPER |
| Insulation | 3/9/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 3/24/2021 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 3/24/2021 | Approved | KENNETH NAGLE |
| Shower Pan | 3/24/2021 | Approved | KENNETH NAGLE |
| Gas Test | 4/14/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 4/14/2021 | Approved | EVAN COOPER |
| Gas Test | 6/22/2021 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 11/4/2021 | Approved | EVAN COOPER |
| Final | 11/4/2021 | Partial Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 11/4/2021 | Approved | EVAN COOPER |
| Green Building Final | 11/4/2021 | Approved | EVAN COOPER |
| HVAC-Final | 11/4/2021 | Approved | EVAN COOPER |
| MERV13>=Final | 11/4/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 11/4/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 11/4/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 11/4/2021 | Approved | EVAN COOPER |
| Structural Steel Frame | 11/4/2021 | Approved | EVAN COOPER |
| Final | 11/8/2021 | OK to Issue CofO | KENNETH NAGLE |