6016 W COMEY AVE 90034

Certificate Information: 6016 W COMEY AVE 90034

Application / Permit
20010-30000-01179
Plan Check / Job No.
B20WL01618
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 2-story SFD with attached garage.
Permit Issued
Issued on 8/12/2020
Issuing Office
Current Status
CofO Issued on 11/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2020 APPLICANT
Assigned to Plan Check Engineer 4/16/2020 MANUEL GARCIA
Corrections Issued 4/21/2020 MANUEL GARCIA
Quality Review Completed 5/1/2020 TARIK SAOUD
Green Plans Picked Up 6/25/2020 APPLICANT
Applicant returned to address corrections 7/8/2020 MANUEL GARCIA
Plan Check Approved 8/11/2020 MANUEL GARCIA
Issued 8/12/2020 APPLICANT
Building Plans Picked Up 8/12/2020 APPLICANT
CofO in Progress 11/8/2021 KENNETH NAGLE
Permit Finaled 11/8/2021 KENNETH NAGLE
CofO Issued 11/8/2021 KENNETH NAGLE
Permit Finaled 11/8/2021 KENNETH NAGLE

Permit Application Clearance Information

Highway dedication Cleared 4/30/2020 RAYMOND MUGAMBWA
Frnt yard landscape/Water mgmt Cleared 5/26/2020 LOUIS ORTEGA
Hydrant and Access approval Cleared 6/4/2020 GEORGE SUCHAND
Low Impact Development Cleared 6/17/2020 SARAH YOUSSEF
Address approval Cleared 6/25/2020 THOMAS LANG
Green Code Cleared 6/25/2020 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 6/26/2020 RENZ SORIANO
Permit Cleared 6/26/2020 RENZ SORIANO
Sewer availability Cleared 6/26/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 7/16/2020 NGOC KIEM

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/10/2020 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 11/17/2020 Approved EVAN COOPER
Deputy Wood Construction 12/7/2020 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 1/21/2021 Partial Approval EVAN COOPER
Sewer 1/21/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Partial Approval EVAN COOPER
Deputy Wood Construction 2/8/2021 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 2/17/2021 Approved EVAN COOPER
HVAC-Rough 2/17/2021 Approved EVAN COOPER
PLUMBING-Rough 3/2/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 3/3/2021 Approved EVAN COOPER
Green Building Rough 3/3/2021 Approved EVAN COOPER
Interior/Exterior Lathing 3/3/2021 Partial Approval EVAN COOPER
MERV13>=Rough 3/3/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 3/3/2021 Approved EVAN COOPER
Insulation 3/9/2021 Approved EVAN COOPER
Drywall Nailing 3/24/2021 Approved KENNETH NAGLE
Interior/Exterior Lathing 3/24/2021 Approved KENNETH NAGLE
Shower Pan 3/24/2021 Approved KENNETH NAGLE
Gas Test 4/14/2021 Partial Approval EVAN COOPER
PLUMBING-Rough 4/14/2021 Approved EVAN COOPER
Gas Test 6/22/2021 Approved EVAN COOPER
ELECTRICAL-Final 11/4/2021 Approved EVAN COOPER
Final 11/4/2021 Partial Inspection EVAN COOPER
Footing/Foundation/Slab 11/4/2021 Approved EVAN COOPER
Green Building Final 11/4/2021 Approved EVAN COOPER
HVAC-Final 11/4/2021 Approved EVAN COOPER
MERV13>=Final 11/4/2021 Approved EVAN COOPER
PLUMBING-Final 11/4/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Approved EVAN COOPER
Service/Power Release 11/4/2021 Approved EVAN COOPER
Smoke Detectors 11/4/2021 Approved EVAN COOPER
Structural Steel Frame 11/4/2021 Approved EVAN COOPER
Final 11/8/2021 OK to Issue CofO KENNETH NAGLE