2227 W STRATFORD CIR 90049
Certificate Information: 2227 W STRATFORD CIR 90049
- Application / Permit
- 20010-30000-01160
- Plan Check / Job No.
- B20WL01598
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 1-STORY TYPE VB PATIO COVER (POOL CABANA)
- Permit Issued
- Issued on 6/4/2020
- Issuing Office
- Current Status
- CofO Corrected on 4/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2020 | SERGIO SILVA |
| Corrections Issued | 4/20/2020 | SERGIO SILVA |
| Green Plans Picked Up | 4/22/2020 | APPLICANT |
| Quality Review Completed | 5/4/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 5/28/2020 | SERGIO SILVA |
| Plan Check Approved | 6/3/2020 | SERGIO SILVA |
| Issued | 6/4/2020 | APPLICANT |
| Building Plans Picked Up | 7/20/2020 | APPLICANT |
| CofO in Progress | 3/17/2022 | CARLOS MATAMOROS |
| CofO Issued-Status Void | 3/22/2022 | DANIEL ORRANTE |
| Permit Finaled-Status Void | 3/22/2022 | DANIEL ORRANTE |
| Re-Activate Permit | 4/19/2022 | DANIEL ORRANTE |
| CofO Corrected | 4/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 4/22/2020 | RICHARD GARCIA |
| Address approval | Cleared | 5/8/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/8/2020 | DINAH GARIN |
| Permit | Cleared | 5/8/2020 | DINAH GARIN |
| Sewer availability | Cleared | 5/8/2020 | DINAH GARIN |
| CPC | Cleared | 5/13/2020 | DENZEL HENDERSON |
| Watercourse | Cleared | 5/15/2020 | MAHELET GEBEYHU |
| Low Impact Development | Cleared | 5/21/2020 | ANDRES COVARRUBIAS |
| Private street | Cleared | 5/21/2020 | NOAH MCCOY |
| Roof/Waste drainage to street | Cleared | 5/21/2020 | MAHELET GEBEYHU |
| Tract Map conditions | Cleared | 5/21/2020 | NOAH MCCOY |
| Tract Map conditions | Cleared | 5/21/2020 | NOAH MCCOY |
| ZA Case | Cleared | 5/21/2020 | NOAH MCCOY |
| Trees in Parkway | Cleared | 5/28/2020 | JOHN KIM |
| GPI Written Notices | Cleared | 6/3/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 6/3/2020 | SERGIO SILVA |
Contact Information
| Architect | , ; Lic. No.: C6452 | , |
| Contractor | Green T C Llc; Lic. No.: 1016145-B | 4831 COOLIDGE AVE CULVER CITY, CA 90230 |
| Engineer | Parker,, Leo Augustine; Lic. No.: S2829 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/17/2020 | Approved | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 7/2/2020 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/2/2020 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 7/7/2020 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/28/2020 | Approved | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 9/28/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/28/2020 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/28/2020 | Approved | CARLOS MATAMOROS |
| Gas Test | 11/5/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 11/6/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Corrections Issued | CARLOS MATAMOROS |
| Underground Mechanical | 11/13/2020 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/16/2020 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 11/17/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/4/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/4/2021 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/18/2021 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/12/2021 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 5/12/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 5/12/2021 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/29/2021 | Approved | CARLOS MATAMOROS |
| Final | 6/29/2021 | OK to Issue CofO | CARLOS MATAMOROS |
| PLUMBING-Final | 6/29/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/29/2021 | Approved | CARLOS MATAMOROS |
| Smoke Detectors | 6/29/2021 | Approved | CARLOS MATAMOROS |