2817 S MANSFIELD AVE 90016

Certificate Information: 2817 S MANSFIELD AVE 90016

Application / Permit
20010-30000-01122
Plan Check / Job No.
B20WL01542
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story ADU per ordinance.
Permit Issued
Issued on 9/18/2020
Issuing Office
Current Status
CofO Issued on 10/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2020 APPLICANT
Assigned to Plan Check Engineer 4/29/2020 MANUEL GARCIA
Corrections Issued 5/6/2020 MANUEL GARCIA
Quality Review Completed 5/11/2020 TARIK SAOUD
Plan Check Approved 9/1/2020 MANUEL GARCIA
Issued 9/18/2020 APPLICANT
Building Plans Picked Up 9/22/2020 APPLICANT
CofO in Progress 9/9/2021 HORACE FULTZ
Permit Finaled 10/5/2021 DEROLD HAUFF
CofO Issued 10/5/2021 DEROLD HAUFF
Permit Finaled 10/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 5/27/2020 RUBEN VASQUEZ
Address approval Cleared 5/28/2020 CECILIO NAVARRO
Highway dedication Cleared 5/28/2020 CECILIO NAVARRO
Permit Cleared 5/28/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/5/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 7/1/2020 KURT CORRAL
Sewer availability Cleared 7/15/2020 PAMELA TENEZA
Construction near power lines Cleared 7/20/2020 RIDWAN HARDY
Low Impact Development Cleared 7/28/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 7/28/2020 CECILIO NAVARRO
Green Code Cleared 8/6/2020 RICHARD GARCIA

Contact Information

Contractor Landmark Builders; Lic. No.: 565610-B 17421 LAHEY STREET      GRANADA HILLS, CA 91344

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Masonry Frame 11/6/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 11/17/2020 Conditional Approval SCOTT FINNILA
Footing/Foundation/Slab 12/9/2020 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Conditional Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/6/2021 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 3/2/2021 Partial Approval SCOTT FINNILA
HVAC-Rough 3/2/2021 Approved SCOTT FINNILA
PLUMBING-Rough 3/2/2021 Approved SCOTT FINNILA
Sewer 3/2/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 3/18/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 3/25/2021 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/25/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 3/25/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 3/25/2021 Partial Approval KATHRYN BUTTERWORTH
Insulation 4/5/2021 Not Ready for Inspection STUART CHAPMAN
Drywall Nailing 4/9/2021 Not Ready for Inspection SABAS ALONSO
Drywall Nailing 4/19/2021 Approved SABAS ALONSO
Gas Test 6/9/2021 Approved STUART CHAPMAN
Service/Power Release 6/30/2021 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 7/15/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 7/15/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 7/15/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/15/2021 Approved CHRISTOPHER DELLEFIELD
Green Building Final 7/15/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 7/15/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 7/15/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 7/15/2021 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 7/15/2021 Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 7/15/2021 Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 7/15/2021 Approved RUBEN SALAS
Verify Sprinkler Sign Off 7/15/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 7/20/2021 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 7/28/2021 Approved SCOTT FINNILA
Final 8/31/2021 OK to Issue CofO HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Approved HORACE FULTZ