2115 N HOLLY DR 90068

Certificate Information: 2115 N HOLLY DR 90068

Application / Permit
20010-30000-01085
Plan Check / Job No.
B20WL01509
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD WITH ATATCHED 2 CAR GARAGE (FRONT)
Permit Issued
Issued on 3/31/2021
Issuing Office
Metro
Current Status
CofO Issued on 8/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2020 APPLICANT
Assigned to Plan Check Engineer 4/22/2020 TARIK SAOUD
Corrections Issued 4/29/2020 TARIK SAOUD
Quality Review Completed 5/8/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/8/2021 TARIK SAOUD
Plan Check Approved 3/1/2021 TARIK SAOUD
Building Plans Picked Up 3/2/2021 APPLICANT
Issued 3/31/2021 APPLICANT
CofO in Progress 8/10/2022 BRIAN SULLIVAN
Permit Finaled 8/13/2022 DEROLD HAUFF
CofO Issued 8/13/2022 DEROLD HAUFF
Permit Finaled 8/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/1/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 9/1/2020 RENZ SORIANO
Sewer availability Cleared 9/1/2020 RENZ SORIANO
Trees in Parkway Cleared 10/1/2020 JOHN KIM
Highway dedication Cleared 10/7/2020 RENZ SORIANO
Permit Cleared 10/7/2020 RENZ SORIANO
Hydrant and Access approval Cleared 12/7/2020 MATTHEW CRAIG
Low Impact Development Cleared 1/21/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/22/2021 RENZ SORIANO
Grading Pre-Inspection Cleared 3/1/2021 TARIK SAOUD

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Azad,, Jila H; Lic. No.: C77585 10636 WILSHIRE BLVD 408      LOS ANGELES, CA 90024
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/7/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 5/14/2021 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 5/14/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/1/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Conditional Approval RICHARD STEINBACH
BUILDING-Rough-Frame 9/15/2021 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/15/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 9/15/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 9/15/2021 Partial Approval FREDDIE RIVERA
MERV13>=Rough 9/15/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Rough 9/15/2021 Approved FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 9/15/2021 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 9/15/2021 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 9/20/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 9/20/2021 Approved BRIAN SULLIVAN
Green Building Rough 9/20/2021 Approved BRIAN SULLIVAN
MERV13>=Rough 9/20/2021 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 9/20/2021 Approved BRIAN SULLIVAN
Drywall Nailing 10/18/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 10/18/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Final 6/6/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 6/6/2022 Not Ready for Inspection BRIAN SULLIVAN
Green Building Final 6/6/2022 Approved BRIAN SULLIVAN
HVAC-Final 6/6/2022 Not Ready for Inspection BRIAN SULLIVAN
MERV13>=Final 6/6/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/6/2022 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/6/2022 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 6/6/2022 Approved BRIAN SULLIVAN
Smoke Detectors 6/6/2022 Approved BRIAN SULLIVAN
ELECTRICAL-Final 6/27/2022 Approved BRIAN SULLIVAN
Final 6/27/2022 Corrections Issued BRIAN SULLIVAN
HVAC-Final 6/27/2022 Approved BRIAN SULLIVAN
PLUMBING-Final 6/27/2022 Approved BRIAN SULLIVAN
Final 8/10/2022 OK to Issue CofO BRIAN SULLIVAN