2115 N HOLLY DR 90068
Certificate Information: 2115 N HOLLY DR 90068
- Application / Permit
- 20010-30000-01085
- Plan Check / Job No.
- B20WL01509
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD WITH ATATCHED 2 CAR GARAGE (FRONT)
- Permit Issued
- Issued on 3/31/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2020 | TARIK SAOUD |
| Corrections Issued | 4/29/2020 | TARIK SAOUD |
| Quality Review Completed | 5/8/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/8/2021 | TARIK SAOUD |
| Plan Check Approved | 3/1/2021 | TARIK SAOUD |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Issued | 3/31/2021 | APPLICANT |
| CofO in Progress | 8/10/2022 | BRIAN SULLIVAN |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
| CofO Issued | 8/13/2022 | DEROLD HAUFF |
| Permit Finaled | 8/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/1/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 9/1/2020 | RENZ SORIANO |
| Trees in Parkway | Cleared | 10/1/2020 | JOHN KIM |
| Highway dedication | Cleared | 10/7/2020 | RENZ SORIANO |
| Permit | Cleared | 10/7/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 12/7/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/21/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/22/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 3/1/2021 | TARIK SAOUD |
Contact Information
| Contractor | Baksh Construction Inc; Lic. No.: 910533-B | 4 HILLCREST MANOR ROLLING HILLS ESTATES, CA 90274 |
| Engineer | Azad,, Jila H; Lic. No.: C77585 | 10636 WILSHIRE BLVD 408 LOS ANGELES, CA 90024 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/7/2021 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/14/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/14/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 9/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 9/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 9/15/2021 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 9/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/15/2021 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 9/15/2021 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/20/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/20/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 9/20/2021 | Approved | BRIAN SULLIVAN |
| MERV13>=Rough | 9/20/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 9/20/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 10/18/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/18/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Final | 6/6/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 6/6/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Final | 6/6/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 6/6/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| MERV13>=Final | 6/6/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 6/6/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 6/6/2022 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 6/6/2022 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 6/27/2022 | Approved | BRIAN SULLIVAN |
| Final | 6/27/2022 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 6/27/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 6/27/2022 | Approved | BRIAN SULLIVAN |
| Final | 8/10/2022 | OK to Issue CofO | BRIAN SULLIVAN |