522-522 1/2 N WILTON PL 90004

Certificate Information: 522-522 1/2 N WILTON PL 90004

Application / Permit
20010-30000-01051
Plan Check / Job No.
B20WL01470
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
New 3 story duplex with attached garage. Front Duplex.
Permit Issued
Issued on 9/15/2020
Issuing Office
Current Status
CofO Issued on 11/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2020 APPLICANT
Assigned to Plan Check Engineer 4/22/2020 MANUEL GARCIA
Corrections Issued 4/28/2020 MANUEL GARCIA
Quality Review Completed 5/5/2020 TARIK SAOUD
Applicant returned to address corrections 5/27/2020 MANUEL GARCIA
Applicant returned to address corrections 6/4/2020 MANUEL GARCIA
Green Plans Picked Up 6/25/2020 APPLICANT
Applicant returned to address corrections 7/7/2020 MANUEL GARCIA
Plan Check Approved 8/13/2020 MANUEL GARCIA
Issued 9/15/2020 APPLICANT
Building Plans Picked Up 9/16/2020 APPLICANT
CofO in Progress 10/31/2021 CHRIS CHRISTENSEN
Permit Finaled 11/6/2021 DEROLD HAUFF
CofO Issued 11/6/2021 DEROLD HAUFF
Permit Finaled 11/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/20/2020 GEORGE SUCHAND
Low Impact Development Cleared 6/3/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 6/11/2020 CELINA MORENO
Highway dedication Cleared 6/11/2020 CELINA MORENO
Permit Cleared 6/11/2020 CELINA MORENO
Certificate of Compliance Cleared 6/16/2020 KENTON TRINH
Frnt yard landscape/Water mgmt Cleared 6/19/2020 KENTON TRINH
Green Code Cleared 6/25/2020 RICHARD GARCIA
Address approval Cleared 7/8/2020 CELINA MORENO
Roof/Waste drainage to street Cleared 7/8/2020 CELINA MORENO
Sewer availability Cleared 7/22/2020 JEANIE LAM
Building over 36-ft Cleared 8/13/2020 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/22/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Underground Mechanical 10/26/2020 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/4/2020 Approved CHRIS CHRISTENSEN
Deputy Steel/Welding 12/10/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Conditional Approval CHRIS CHRISTENSEN
Deputy Wood Construction 2/16/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/30/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 3/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 3/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 3/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Shower Pan 4/5/2021 Approved CHRIS CHRISTENSEN
Wood Frame 4/5/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/8/2021 Conditional Approval CHRIS CHRISTENSEN
HVAC-Rough 4/8/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/8/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/16/2021 Partial Approval ROBERT VORHIS
BUILDING-Rough-Frame 4/27/2021 Conditional Approval ROBERT VORHIS
Green Building Rough 4/27/2021 Approved ROBERT VORHIS
Insulation 4/27/2021 Approved ROBERT VORHIS
Verify Sprinkler Sign Off 4/27/2021 Approved ROBERT VORHIS
Drywall Nailing 5/10/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/12/2021 Approved ROBERT VORHIS
ELECTRICAL-Final 9/3/2021 Approved ARTHUR SARGSYAN
Service/Power Release 9/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Final 9/7/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 9/7/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 9/7/2021 Approved CHRIS CHRISTENSEN
Service/Power Release 9/7/2021 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/22/2021 Approved CHRIS CHRISTENSEN
Final 10/22/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 10/22/2021 Approved CHRIS CHRISTENSEN
Green Building Final 10/22/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 10/22/2021 Not Required CHRIS CHRISTENSEN
Smoke Detectors 10/22/2021 Approved CHRIS CHRISTENSEN
Final 10/29/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 10/29/2021 Approved CHRIS CHRISTENSEN