11361 W CLOVER AVE 90066
Certificate Information: 11361 W CLOVER AVE 90066
- Application / Permit
- 20010-30000-01041
- Plan Check / Job No.
- B20WL01455
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 11/9/2020
- Issuing Office
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2020 | SERGIO SILVA |
| Corrections Issued | 5/4/2020 | SERGIO SILVA |
| Quality Review Completed | 5/11/2020 | TARIK SAOUD |
| Green Plans Picked Up | 5/27/2020 | APPLICANT |
| Applicant returned to address corrections | 6/18/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 10/20/2020 | SERGIO SILVA |
| Plan Check Approved | 11/6/2020 | SERGIO SILVA |
| Issued | 11/9/2020 | APPLICANT |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| CofO in Progress | 11/17/2021 | KENNETH NAGLE |
| Permit Finaled | 11/17/2021 | KENNETH NAGLE |
| CofO Issued | 11/17/2021 | KENNETH NAGLE |
| Permit Finaled | 11/17/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 5/4/2020 | JOHN KIM |
| Address approval | Cleared | 7/29/2020 | DINAH GARIN |
| Permit | Cleared | 7/30/2020 | DINAH GARIN |
| Sewer availability | Cleared | 7/30/2020 | DINAH GARIN |
| CPC | Cleared | 8/31/2020 | LOUIS ORTEGA |
| CPC | Cleared | 8/31/2020 | LOUIS ORTEGA |
| Hydrant and Access approval | Cleared | 9/9/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 9/16/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 9/22/2020 | DINAH GARIN |
| Specific Plan | Cleared | 9/29/2020 | FREDDY GARCIA |
| GPI Written Notices | Cleared | 10/20/2020 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 10/20/2020 | SERGIO SILVA |
| Green Code | Cleared | 10/21/2020 | RICHARD GARCIA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy Wayne; Lic. No.: C37316 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/26/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 3/26/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/1/2021 | Corrections Issued | EVAN COOPER |
| Deputy Drilled-In Anchors | 4/6/2021 | Conditional Approval | EVAN COOPER |
| Deputy Other (see comments) | 4/6/2021 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 4/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 4/14/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 4/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 4/14/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 5/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Shower Pan | 5/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Special/Order Compliance | 5/14/2021 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 5/20/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 5/20/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 5/20/2021 | Approved | EVAN COOPER |
| Sewer | 5/20/2021 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 5/20/2021 | Approved | EVAN COOPER |
| Sewer | 5/28/2021 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/7/2021 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 6/7/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 6/7/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/7/2021 | Partial Approval | EVAN COOPER |
| Sewer | 6/7/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/7/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 6/21/2021 | Approved | EVAN COOPER |
| Insulation | 6/21/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/21/2021 | Partial Approval | EVAN COOPER |
| Verify Sprinkler Sign Off | 6/21/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 7/1/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/1/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 9/20/2021 | Approved | OGANES TARAKHCHYAN |
| Verify Rec and Parks Fee Memo | 9/21/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 9/23/2021 | Approved | EVAN COOPER |
| HVAC-Final | 10/12/2021 | Not Ready for Inspection | ANDREW NAVE |
| Final | 11/5/2021 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/5/2021 | Approved | EVAN COOPER |
| Green Building Final | 11/5/2021 | Approved | EVAN COOPER |
| HVAC-Final | 11/5/2021 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/5/2021 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 11/5/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 11/5/2021 | Approved | EVAN COOPER |