440 N SLOAT ST 90063

Certificate Information: 440 N SLOAT ST 90063

Application / Permit
20010-30000-01016
Plan Check / Job No.
B20WL01406
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Single family dwelling with attached garage. Equipped with fire sprinkler system NFPA-13D.
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 5/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 ALFREDO JARA
Corrections Issued 4/13/2020 ALFREDO JARA
Quality Review Completed 4/24/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 7/21/2020 APPLICANT
Plan Check Approved 1/19/2021 ALFREDO JARA
Issued 1/25/2021 APPLICANT
Building Plans Picked Up 1/27/2021 APPLICANT
CofO in Progress 5/12/2023 OSVALDO PARAMO
CofO in Progress 5/12/2023 OSVALDO PARAMO
Permit Finaled 5/25/2023 DEROLD HAUFF
CofO Issued 5/25/2023 DEROLD HAUFF
Permit Finaled 5/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/27/2020 VASIL MIHALEV
Address approval Cleared 7/6/2020 WALLIE JONG
Permit Cleared 7/7/2020 WALLIE JONG
Sewer availability Cleared 7/7/2020 WALLIE JONG
Trees in Parkway Cleared 7/14/2020 JOHN KIM
Eng Process Fee Ord 176,300 Cleared 7/20/2020 WALLIE JONG
Green Code Cleared 7/20/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 8/25/2020 MATTHEW CRAIG
Low Impact Development Cleared 9/24/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 9/24/2020 CELINA MORENO
GPI Written Notices Cleared 1/19/2021 VASIL MIHALEV

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/10/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/10/2021 Corrections Issued SCOTT FINNILA
METHANE-Barrier 3/10/2021 Partial Inspection SCOTT FINNILA
METHANE-Subgrade 3/10/2021 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/23/2021 Corrections Issued OSVALDO PARAMO
METHANE-Barrier 3/23/2021 Approved OSVALDO PARAMO
METHANE-Subgrade 3/23/2021 Approved OSVALDO PARAMO
Footing/Foundation/Slab 4/5/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 4/26/2021 Partial Approval OSVALDO PARAMO
Wood Frame 4/26/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Partial Approval OSVALDO PARAMO
Insulation 5/5/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 No Access for Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 1/19/2022 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 2/2/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Approved OSVALDO PARAMO
HVAC-Rough 2/2/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 2/2/2022 Approved OSVALDO PARAMO
Underground Mechanical 2/9/2022 Partial Approval COREY HUPP
BUILDING-Rough-Frame 3/1/2022 Approved OSVALDO PARAMO
Green Building Rough 3/1/2022 Approved OSVALDO PARAMO
HVAC-Rough 3/1/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/1/2022 Partial Approval OSVALDO PARAMO
METHANE-Rough 3/1/2022 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 3/1/2022 Approved OSVALDO PARAMO
Insulation 3/10/2022 Approved OSVALDO PARAMO
Drywall Nailing 3/16/2022 Approved RUBEN SALAS
Final 4/14/2023 Corrections Issued OSVALDO PARAMO
Green Building Final 4/14/2023 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 4/14/2023 SGSOV Approved OSVALDO PARAMO
Service/Power Release 4/14/2023 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 4/14/2023 Approved OSVALDO PARAMO
ELECTRICAL-Final 4/25/2023 Approved OSVALDO PARAMO
Final 4/25/2023 Partial Inspection OSVALDO PARAMO
HVAC-Final 4/25/2023 Approved OSVALDO PARAMO
PLUMBING-Final 4/25/2023 Approved OSVALDO PARAMO
Service/Power Release 4/25/2023 Not Ready for Inspection OSVALDO PARAMO
Final 5/11/2023 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 5/11/2023 Approved OSVALDO PARAMO