171 S HOOVER ST 1-2 90004

Certificate Information: 171 S HOOVER ST 1-2 90004

Application / Permit
20010-30000-00914
Plan Check / Job No.
B20WL01314
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3 -STORY TYPE VB DUPLEX EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 1/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 SERGIO SILVA
Corrections Issued 4/13/2020 SERGIO SILVA
Quality Review Completed 4/23/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 7/8/2020 SERGIO SILVA
Green Plans Picked Up 8/14/2020 APPLICANT
Applicant returned to address corrections 9/24/2020 SERGIO SILVA
Plan Check Approved 11/20/2020 SERGIO SILVA
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 6/15/2022 APPLICANT
CofO in Progress 1/16/2024 KATHRYN BUTTERWORTH
Permit Finaled 1/21/2024 DEROLD HAUFF
CofO Issued 1/21/2024 DEROLD HAUFF
Permit Finaled 1/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 5/22/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/26/2020 WALLIE JONG
Trees in Parkway Cleared 6/2/2020 JOHN KIM
Opn space landscape/Water mgmt Cleared 6/5/2020 ANACANY HURTADO
Address approval Cleared 6/15/2020 WALLIE JONG
Sewer availability Cleared 6/16/2020 WALLIE JONG
Frnt yard landscape/Water mgmt Cleared 7/8/2020 ANACANY HURTADO
Low Impact Development Cleared 7/22/2020 ORVAL HERNANDEZ-MARCI
Methane Ordinance Cleared 7/28/2020 VIDAL GARCIA
Roof/Waste drainage to street Cleared 7/29/2020 WALLIE JONG
Green Code Cleared 8/13/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 8/27/2020 MATTHEW CRAIG
Miscellaneous Cleared 9/24/2020 SERGIO SILVA
Miscellaneous Cleared 9/24/2020 SERGIO SILVA
GPI Written Notices Cleared 10/14/2020 SERGIO SILVA
Grading Pre-Inspection Cleared 10/26/2020 BARTON HOLMES

Contact Information

Contractor On Point Builders Inc; Lic. No.: 928105-B 2371 GRAND AVE #90902      LONG BEACH, CA 90809
Engineer Moeini,, Soheil; Lic. No.: C84000 1836 PARNELL AVE 202      LOS ANGELES, CA 90025
Engineer Shubeck,, Robert James; Lic. No.: GE773 60 HACKAMORE LANE      BELL CANYON, CA 91307

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/19/2022 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 5/31/2022 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/28/2022 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 6/28/2022 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 6/28/2022 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 6/28/2022 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 7/12/2022 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 7/19/2022 Corrections Issued KATHRYN BUTTERWORTH
Sewer 7/19/2022 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 9/13/2022 Partial Approval KATHRYN BUTTERWORTH
Special/Order Compliance 9/13/2022 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 2/1/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 2/1/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 2/9/2023 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 2/9/2023 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/24/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/24/2023 Approved KATHRYN BUTTERWORTH
Green Building Rough 3/24/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 3/24/2023 Approved KATHRYN BUTTERWORTH
METHANE-Rough 3/24/2023 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 3/24/2023 Approved KATHRYN BUTTERWORTH
Insulation 4/13/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/13/2023 Partial Inspection KATHRYN BUTTERWORTH
Insulation 4/21/2023 Approved KATHRYN BUTTERWORTH
Drywall Nailing 5/12/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/12/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Final 11/14/2023 No Access for Inspection KATHRYN BUTTERWORTH
HVAC-Final 11/14/2023 No Access for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 11/14/2023 No Access for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/20/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 11/20/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 11/20/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 11/20/2023 Approved KATHRYN BUTTERWORTH
HVAC-Final 11/20/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 11/20/2023 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 11/20/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 11/20/2023 Approved KATHRYN BUTTERWORTH
Final 1/3/2024 Corrections Issued KATHRYN BUTTERWORTH
Service/Power Release 1/3/2024 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 1/9/2024 OK to Issue CofO KATHRYN BUTTERWORTH
Service/Power Release 1/9/2024 Approved KATHRYN BUTTERWORTH