4036 1/2 S DALTON AVE 90062

Certificate Information: 4036 1/2 S DALTON AVE 90062

Application / Permit
20010-30000-00904
Plan Check / Job No.
B20WL01295
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD WITH ATTACHED GARAGE AND REC ROOM AT REAR OF THE LOT.
Permit Issued
Issued on 1/7/2021
Issuing Office
Current Status
CofO Issued on 1/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/16/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 JAHANSHAH POURHASSAN
Corrections Issued 4/9/2020 JAHANSHAH POURHASSAN
Quality Review Completed 4/17/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 7/17/2020 APPLICANT
Plan Check Approved 11/20/2020 JAHANSHAH POURHASSAN
Building Plans Picked Up 11/23/2020 APPLICANT
Issued 1/7/2021 APPLICANT
CofO in Progress 10/15/2021 SABAS ALONSO
Permit Finaled 1/6/2022 DEROLD HAUFF
CofO Issued 1/6/2022 DEROLD HAUFF
Permit Finaled 1/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/3/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/4/2020 WALLIE JONG
Sewer availability Cleared 7/1/2020 WALLIE JONG
Green Code Cleared 7/17/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/28/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/3/2020 CELINA MORENO

Contact Information

Contractor Perez Alvarado Herbert; Lic. No.: 1058036-B 12412 BECK AVE      GARDEN GROVE, CA 92840
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/11/2021 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 2/9/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Partial Approval ROBERT MCDOWELL
BUILDING-Rough-Frame 3/31/2021 Not Ready for Inspection ROBERT MCDOWELL
ELECTRICAL-Rough 3/31/2021 Approved ROBERT MCDOWELL
Green Building Rough 3/31/2021 Not Ready for Inspection ROBERT MCDOWELL
PLUMBING-Rough 3/31/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/31/2021 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 4/13/2021 Corrections Issued FREDDIE RIVERA
Gas Test 4/13/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 4/13/2021 Not Ready for Inspection FREDDIE RIVERA
Sewer 4/13/2021 Not Ready for Inspection DAVID FEILER
Underground Mechanical 4/13/2021 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 4/13/2021 Not Ready for Inspection FREDDIE RIVERA
Gas Test 4/29/2021 Partial Approval ROBERT MCDOWELL
HVAC-Rough 4/29/2021 Approved ROBERT MCDOWELL
Sewer 4/29/2021 Approved ROBERT MCDOWELL
Underground Mechanical 4/29/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 5/10/2021 Conditional Approval ROBERT MCDOWELL
Insulation 5/10/2021 Approved ROBERT MCDOWELL
Drywall Nailing 5/19/2021 Approved ROBERT MCDOWELL
Green Building Rough 5/19/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 5/19/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 9/22/2021 Conditional Approval SABAS ALONSO
Final 9/22/2021 Corrections Issued SABAS ALONSO
Gas Test 9/22/2021 Approved SABAS ALONSO
Green Building Final 9/22/2021 Not Ready for Inspection SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 9/22/2021 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 9/22/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 9/22/2021 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 10/14/2021 Approved SABAS ALONSO
Final 10/14/2021 OK to Issue CofO SABAS ALONSO
Green Building Final 10/14/2021 Approved SABAS ALONSO
Service/Power Release 10/14/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 10/14/2021 Approved SABAS ALONSO