4036 1/2 S DALTON AVE 90062
Certificate Information: 4036 1/2 S DALTON AVE 90062
- Application / Permit
- 20010-30000-00904
- Plan Check / Job No.
- B20WL01295
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD WITH ATTACHED GARAGE AND REC ROOM AT REAR OF THE LOT.
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofO Issued on 1/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 4/9/2020 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 4/17/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/17/2020 | APPLICANT |
| Plan Check Approved | 11/20/2020 | JAHANSHAH POURHASSAN |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Issued | 1/7/2021 | APPLICANT |
| CofO in Progress | 10/15/2021 | SABAS ALONSO |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
| CofO Issued | 1/6/2022 | DEROLD HAUFF |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | WALLIE JONG |
| Sewer availability | Cleared | 7/1/2020 | WALLIE JONG |
| Green Code | Cleared | 7/17/2020 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 8/17/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/28/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/3/2020 | CELINA MORENO |
Contact Information
| Contractor | Perez Alvarado Herbert; Lic. No.: 1058036-B | 12412 BECK AVE GARDEN GROVE, CA 92840 |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/11/2021 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 2/9/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Partial Approval | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/31/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/31/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/31/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/31/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 3/31/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 4/13/2021 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 4/13/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Sewer | 4/13/2021 | Not Ready for Inspection | DAVID FEILER |
| Underground Mechanical | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Gas Test | 4/29/2021 | Partial Approval | ROBERT MCDOWELL |
| HVAC-Rough | 4/29/2021 | Approved | ROBERT MCDOWELL |
| Sewer | 4/29/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 4/29/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/10/2021 | Conditional Approval | ROBERT MCDOWELL |
| Insulation | 5/10/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 5/19/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/19/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 5/19/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 9/22/2021 | Conditional Approval | SABAS ALONSO |
| Final | 9/22/2021 | Corrections Issued | SABAS ALONSO |
| Gas Test | 9/22/2021 | Approved | SABAS ALONSO |
| Green Building Final | 9/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/22/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 9/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 9/22/2021 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 9/22/2021 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | SABAS ALONSO |
| Final | 10/14/2021 | OK to Issue CofO | SABAS ALONSO |
| Green Building Final | 10/14/2021 | Approved | SABAS ALONSO |
| Service/Power Release | 10/14/2021 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 10/14/2021 | Approved | SABAS ALONSO |