6255 W MEMORY LANE 90045
Certificate Information: 6255 W MEMORY LANE 90045
- Application / Permit
- 20010-30000-00875
- Plan Check / Job No.
- B20WL01256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY SFD W/ ATT. 2-CAR GARAGE (SUB-DIVISION - LOT C)
- Permit Issued
- Issued on 7/21/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2020 | REZA HAGHIGHAT |
| Corrections Issued | 4/13/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 4/24/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/1/2020 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 7/24/2020 | REZA HAGHIGHAT |
| Building Plans Picked Up | 7/29/2020 | APPLICANT |
| Green Plans Picked Up | 7/29/2020 | APPLICANT |
| Applicant returned to address corrections | 5/5/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/10/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/11/2021 | REZA HAGHIGHAT |
| Plan Check Approved | 6/9/2021 | REZA HAGHIGHAT |
| Issued | 7/21/2021 | APPLICANT |
| CofO in Progress | 2/26/2026 | DAVID FEILER |
| Permit Finaled | 2/26/2026 | RICHARD STEINBACH |
| CofO Issued | 2/26/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/26/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 4/29/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 7/27/2020 | RICHARD GARCIA |
| Address approval | Cleared | 8/19/2020 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 10/14/2020 | TAO YANG |
| Permit | Cleared | 10/14/2020 | TAO YANG |
| Low Impact Development | Cleared | 12/23/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/6/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 2/22/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 3/23/2021 | NOAH MCCOY |
| Miscellaneous | Cleared | 3/23/2021 | NOAH MCCOY |
| Private street | Cleared | 3/23/2021 | NOAH MCCOY |
| Trees in Parkway | Cleared | 4/13/2021 | JOHN KIM |
| GPI Written Notices | Cleared | 5/5/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 5/5/2021 | REZA HAGHIGHAT |
| Green Code | Cleared | 5/5/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | Pillar Building Group Llc; Lic. No.: 1017041-B | 8109 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Geologist | , ; Lic. No.: GEO2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 9/24/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 9/24/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/4/2021 | Approved | DAVID FEILER |
| METHANE-Barrier | 11/4/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Approved | DAVID FEILER |
| Gas Test | 4/11/2022 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 4/11/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 4/11/2022 | Approved | DAVID FEILER |
| Sewer | 4/11/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 6/23/2022 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 6/23/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 6/23/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 6/23/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 6/23/2022 | Partial Approval | DAVID FEILER |
| METHANE-Rough | 6/23/2022 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 6/23/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 8/12/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 8/12/2022 | Approved | DAVID FEILER |
| Insulation | 8/12/2022 | Conditional Approval | DAVID FEILER |
| Drywall Nailing | 9/12/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 12/14/2022 | Approved | HERBERT GIRON |
| Shower Pan | 12/14/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 3/18/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 6/25/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 10/31/2024 | Corrections Issued | MICHAEL ALLEN |
| Service/Power Release | 10/31/2024 | Not Ready for Inspection | MICHAEL ALLEN |
| ELECTRICAL-Final | 11/5/2024 | Approved | MICHAEL ALLEN |
| Service/Power Release | 11/5/2024 | Corrections Issued | MICHAEL ALLEN |
| Service/Power Release | 12/19/2024 | Approved | DAVID FEILER |
| Gas Test | 4/24/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 4/24/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 4/24/2025 | Approved | RUBEN RIVAS |
| Final | 2/25/2026 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 2/25/2026 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 2/25/2026 | Approved | DAVID FEILER |