152 E 104TH ST 90003
Certificate Information: 152 E 104TH ST 90003
- Application / Permit
- 20010-30000-00861
- Plan Check / Job No.
- B20WL01243
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Current Status
- CofO Issued on 10/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2020 | MANUEL GARCIA |
| Corrections Issued | 4/2/2020 | MANUEL GARCIA |
| Quality Review Completed | 4/8/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 4/16/2020 | APPLICANT |
| Green Plans Picked Up | 7/24/2020 | APPLICANT |
| Applicant returned to address corrections | 1/27/2021 | MANUEL GARCIA |
| Applicant returned to address corrections | 6/23/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 3/15/2022 | FELIPE HERNANDEZ |
| Issued | 4/14/2022 | APPLICANT |
| CofO in Progress | 10/16/2023 | JOHN KLARIN |
| CofO Issued | 10/19/2023 | ANSON MAGLASANG |
| Permit Finaled | 10/19/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| ZI | Cleared | 6/12/2020 | JASON CHAN |
| Address approval | Cleared | 6/15/2020 | CELINA MORENO |
| Green Code | Cleared | 6/19/2020 | RICHARD GARCIA |
| Sewer availability | Cleared | 7/17/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/27/2020 | CELINA MORENO |
| Construction near power lines | Cleared | 9/21/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/15/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/9/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 1/25/2021 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 11/12/2021 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 8/26/2022 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 9/8/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 9/20/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 9/20/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 10/13/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 10/13/2022 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/1/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 11/9/2022 | Not Ready for Inspection | JOHN KLARIN |
| Interior/Exterior Lathing | 11/9/2022 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 11/9/2022 | Corrections Issued | JOHN KLARIN |
| Insulation | 11/15/2022 | Corrections Issued | JOHN KLARIN |
| Interior/Exterior Lathing | 11/15/2022 | Conditional Approval | JOHN KLARIN |
| Insulation | 12/15/2022 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 12/15/2022 | Approved | JOHN KLARIN |
| Drywall Nailing | 12/27/2022 | Approved | JOHN KLARIN |
| Green Building Rough | 12/27/2022 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 8/8/2023 | Approved | JOHN KLARIN |
| Final | 8/8/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/8/2023 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Not Ready | JOHN KLARIN |
| Service/Power Release | 8/8/2023 | Not Ready for Inspection | JOHN KLARIN |
| Smoke Detectors | 8/8/2023 | Approved | JOHN KLARIN |
| Final | 8/18/2023 | Corrections Issued | JOHN KLARIN |
| Green Building Final | 8/18/2023 | Approved | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | JOHN KLARIN |
| Service/Power Release | 8/18/2023 | Not Ready for Inspection | JOHN KLARIN |
| Final | 9/8/2023 | Corrections Issued | JOHN KLARIN |
| Service/Power Release | 9/8/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Final | 10/13/2023 | Approved | JOHN KLARIN |
| Final | 10/13/2023 | OK to Issue CofO | JOHN KLARIN |
| HVAC-Final | 10/13/2023 | Approved | JOHN KLARIN |
| PLUMBING-Final | 10/13/2023 | Approved | JOHN KLARIN |
| Service/Power Release | 10/13/2023 | Approved | JOHN KLARIN |