4152 N CAHUENGA BLVD 1-3 91602

Certificate Information: 4152 N CAHUENGA BLVD 1-3 91602

Application / Permit
20010-30000-00820
Plan Check / Job No.
B20WL01186
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3-Unit 3 story Townhouses with attached garage (Units 8 to 10)
Permit Issued
Issued on 12/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2020 APPLICANT
Assigned to Plan Check Engineer 4/2/2020 MARJAN SHENASI
Corrections Issued 4/9/2020 MARJAN SHENASI
Quality Review Completed 4/17/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/20/2020 APPLICANT
Green Plans Picked Up 8/6/2020 APPLICANT
Applicant returned to address corrections 5/11/2022 TARIK SAOUD
Applicant returned to address corrections 9/26/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/6/2022 KAVIAN REFAHI
Applicant returned to address corrections 10/17/2022 KAVIAN REFAHI
Plan Check Approved 11/4/2022 KAVIAN REFAHI
Issued 12/16/2022 APPLICANT
CofO in Progress 2/13/2026 DEANDRE HOFFMAN
Permit Finaled 2/13/2026 JEFFREY DURAN
CofO Issued 2/13/2026 JEFFREY DURAN
Permit Finaled 2/13/2026 JEFFREY DURAN

Permit Application Clearance Information

Low Impact Development Cleared 3/3/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/15/2022 CARLOS AGUILERA
Address approval Cleared 6/27/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/28/2022 CARLOS AGUILERA
Sewer availability Cleared 6/28/2022 CARLOS AGUILERA
Highway dedication Cleared 6/29/2022 CARLOS AGUILERA
Permit Cleared 6/29/2022 CARLOS AGUILERA
Disturb/Remove Protected Trees Cleared 6/30/2022 ADALBERTO VERA
Green Code Cleared 8/11/2022 AARON COSTA
Trees in Parkway Cleared 9/1/2022 ADALBERTO VERA
DAS Clearance Cleared 9/6/2022 MARJAN SHENASI
Driveway location Cleared 9/7/2022 MIGUEL CRISOSTOMO
Frnt yard landscape/Water mgmt Cleared 9/7/2022 YINGSHI HUANG
Hydrant and Access approval Cleared 9/7/2022 JOHN CONNEALLY
Opn space landscape/Water mgmt Cleared 9/7/2022 YINGSHI HUANG
ZI Cleared 9/7/2022 YINGSHI HUANG

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor G L E Inc; Lic. No.: 733205-B 17328 VENTURA BLVD #182      ENCINO, CA 91316
Engineer Farag,, Amgad N; Lic. No.: C74076 27050 MAPLE TREE CT      VALENCIA, CA 91381

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready JOHN KITCKO
Special/Order Compliance 5/26/2023 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 6/26/2023 Corrections Issued JOHN KITCKO
Piling/Pier/Caisson 6/26/2023 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 6/26/2023 Not Ready for Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 7/3/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 7/24/2023 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 8/30/2023 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 9/15/2023 Partial Approval JOHN KITCKO
Deputy Wood Construction 10/5/2023 Conditional Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 2/7/2024 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 2/8/2024 Not Ready for Inspection JOHN KITCKO
Insulation 2/15/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 2/15/2024 Partial Inspection JOHN KITCKO
Special/Order Compliance 2/16/2024 Partial Inspection JOHN KITCKO
Insulation 2/23/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 2/23/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 4/9/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 4/9/2024 Approved JOHN KITCKO
Wood Frame 4/9/2024 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 4/10/2024 Conditional Approval JOHN KITCKO
Special/Order Compliance 4/11/2024 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 4/18/2024 Partial Approval DANIEL VARNUM
Insulation 4/22/2024 Not Ready for Inspection JOHN KITCKO
Insulation 4/23/2024 Not Ready for Inspection JOHN KITCKO
Special/Order Compliance 4/23/2024 Not Ready for Inspection JOHN KITCKO
Insulation 4/26/2024 Partial Approval JOHN KITCKO
Special/Order Compliance 4/26/2024 Partial Inspection JOHN KITCKO
Drywall Nailing 4/30/2024 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 5/6/2024 Approved JOHN KITCKO
Interior/Exterior Lathing 5/6/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 5/21/2024 Approved JOHN KITCKO
Special/Order Compliance 5/21/2024 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 6/17/2024 Partial Approval JOHN KITCKO
Final 10/30/2024 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 10/30/2024 Approved JOHN KITCKO
Green Building Final 10/30/2024 Not Ready for Inspection JOHN KITCKO
Green Building Rough 10/30/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Not Ready JOHN KITCKO
Smoke Detectors 10/30/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 10/30/2024 Approved JOHN KITCKO
Special/Order Compliance 3/14/2025 Partial Inspection JOHN KITCKO
T-Bar Ceiling 6/13/2025 Corrections Issued JOHN KITCKO
Final 1/27/2026 OK to Issue CofO DEANDRE HOFFMAN
Green Building Final 1/27/2026 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 1/27/2026 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 1/27/2026 Approved DEANDRE HOFFMAN