9210 W ROBIN DR 90069
Certificate Information: 9210 W ROBIN DR 90069
- Application / Permit
- 20010-30000-00798
- Plan Check / Job No.
- B20WL01158
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (n) ALQ
- Permit Issued
- Issued on 10/8/2021
- Issuing Office
- Current Status
- Issued on 10/8/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/25/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 4/17/2020 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 4/21/2020 | APPLICANT |
| Quality Review Completed | 4/24/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/18/2020 | APPLICANT |
| Plan Check Approved | 9/8/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 10/8/2021 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/2/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 6/2/2020 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 6/2/2020 | JEANIE LAM |
| Permit | Cleared | 6/2/2020 | JEANIE LAM |
| Sewer availability | Cleared | 6/2/2020 | JEANIE LAM |
| Excavation more than 5-ft deep | Cleared | 7/8/2020 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 8/10/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 8/20/2020 | JOHN KIM |
| Low Impact Development | Cleared | 10/23/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | PAMELA TENEZA |
| Disturb/Remove Protected Trees | Cleared | 1/27/2021 | VLADIMIR ARUTYUNYAN |
| Miscellaneous | Cleared | 2/8/2021 | LINDA MARGARET |
| Miscellaneous | Cleared | 2/8/2021 | LINDA MARGARET |
| Roof/Waste drainage to street | Cleared | 2/8/2021 | SAM NAVID |
| Green Code | Cleared | 9/8/2021 | RICHARD GARCIA |
Contact Information
| Architect | Takacs,, David Alexander; Lic. No.: C33737 | 824 S. LOS ANGELES STREET LOS ANGELES, CA 90014 |
| Contractor | View Site Development Llc; Lic. No.: 1001072-B | 10800 BURBANK BLVD STE A NORTH HOLLYWOOD, CA 91601 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/15/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 5/15/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/16/2024 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 5/17/2024 | Partial Inspection | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/3/2024 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/3/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/10/2024 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/15/2024 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 7/16/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/17/2024 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 7/24/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/6/2024 | Partial Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/12/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 8/15/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/16/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/20/2024 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 9/6/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 10/9/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/11/2024 | Partial Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/12/2024 | Corrections Issued | BRENDAN MORELLI |
| Reinforced Concrete Frame | 11/13/2024 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 12/2/2024 | Partial Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 12/16/2024 | No Access for Inspection | AMIR NAZARIAN |
| Light Gage Steel Frame | 12/18/2024 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 1/28/2025 | No Access for Inspection | ROY SPAULDING |
| Footing/Foundation/Slab | 1/29/2025 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/27/2025 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 2/27/2025 | Partial Approval | RAUL BARAJAS |
| Gas Test | 3/11/2025 | Partial Approval | ROY SPAULDING |
| Underground Mechanical | 3/24/2025 | Partial Approval | ROY SPAULDING |
| Underground Mechanical | 4/10/2025 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 4/16/2025 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Partial Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 6/13/2025 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Conditional Approval | SCOTT FINNILA |
| HVAC-Rough | 3/4/2026 | Partial Approval | DAVID WILLIAMS |
| Deputy Steel/Welding | 4/1/2026 | Conditional Approval | DAVID WILLIAMS |
| Structural Steel Frame | 4/1/2026 | Partial Approval | DAVID WILLIAMS |
| Structural Steel Frame | 4/6/2026 | Partial Approval | CRAIG VAUGHAN |
| Structural Steel Frame | 4/28/2026 | Partial Approval | ROY SPAULDING |