4340 N BELLINGHAM AVE 91604
Certificate Information: 4340 N BELLINGHAM AVE 91604
- Application / Permit
- 20010-30000-00592
- Plan Check / Job No.
- B20WL00935
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) 2-story house with attached one car garage and roof trusses.
- Permit Issued
- Issued on 5/22/2020
- Issuing Office
- Current Status
- CofO Issued on 10/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 3/23/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 3/27/2020 | CORA JOHNSON |
| Green Plans Picked Up | 5/14/2020 | APPLICANT |
| Plan Check Approved | 5/21/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 5/22/2020 | APPLICANT |
| Building Plans Picked Up | 5/28/2020 | APPLICANT |
| CofO in Progress | 7/2/2021 | ARAM AVEDISIAN |
| CofO Issued | 10/15/2021 | MICHAEL SMITH |
| Permit Finaled | 10/15/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 4/6/2020 | JOHN KIM |
| Low Impact Development | Cleared | 4/13/2020 | MARTIN FRAGOSO |
| Address approval | Cleared | 4/16/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2020 | DINAH GARIN |
| Permit | Cleared | 4/16/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 4/16/2020 | DINAH GARIN |
| Sewer availability | Cleared | 4/16/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 4/28/2020 | KURT CORRAL |
| Green Code | Cleared | 5/13/2020 | RICHARD GARCIA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/10/2020 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 9/17/2020 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 9/18/2020 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2020 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/16/2020 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/25/2020 | No Access for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 11/25/2020 | No Access for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/25/2020 | No Access for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/7/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 1/7/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/7/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/7/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 1/14/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 1/14/2021 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/20/2021 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 1/20/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/20/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/20/2021 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 1/20/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/2/2021 | Approved | BRENDAN LOONEY |
| Insulation | 2/2/2021 | Conditional Approval | BRENDAN LOONEY |
| Shower Pan | 2/2/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 2/17/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/19/2021 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 3/30/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/7/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 4/7/2021 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Final | 4/7/2021 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 4/14/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 4/22/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 4/30/2021 | Not Ready for Inspection | CHARLES POWELL |
| Final | 5/6/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/6/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 5/6/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 5/6/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 5/6/2021 | Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/6/2021 | Approved | ARAM AVEDISIAN |
| Verify Rec and Parks Fee Memo | 5/6/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 7/2/2021 | OK to Issue CofO | ARAM AVEDISIAN |