10349 W WOODBRIDGE ST 91602
Certificate Information: 10349 W WOODBRIDGE ST 91602
- Application / Permit
- 20010-30000-00542
- Plan Check / Job No.
- B20WL00844
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story s.f.d. w/ basement
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/12/2020 | KAVIAN REFAHI |
| Corrections Issued | 3/18/2020 | KAVIAN REFAHI |
| Quality Review Completed | 3/27/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/7/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/8/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/16/2020 | KAVIAN REFAHI |
| Green Plans Picked Up | 7/27/2020 | APPLICANT |
| Applicant returned to address corrections | 9/30/2020 | KAVIAN REFAHI |
| Applicant returned to address corrections | 11/24/2020 | KAVIAN REFAHI |
| Plan Check Approved | 12/8/2020 | KAVIAN REFAHI |
| Issued | 12/11/2020 | APPLICANT |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
| CofO in Progress | 1/22/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
| CofO Issued | 2/6/2025 | RUBEN SALAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2020 | GUILLERMO PETRA |
| ZA Case | Cleared | 4/13/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 4/13/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 7/17/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 8/10/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/9/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | GUILLERMO PETRA |
| ZI | Cleared | 12/3/2020 | LOUIS ORTEGA |
| Excavation more than 5-ft deep | Cleared | 12/8/2020 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 12/8/2020 | KAVIAN REFAHI |
Contact Information
| Contractor | Building Inc Construction; Lic. No.: 908685-B | 5820 WILSHIRE BLVD 400 LOS ANGELES, CA 90036 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 1/6/2021 | Conditional Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 1/6/2021 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/15/2021 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 4/26/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/1/2021 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 6/25/2021 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 6/28/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/28/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 8/13/2021 | Partial Approval | THOMAS FINNILA |
| Light Gage Steel Frame | 12/20/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 3/10/2022 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/5/2022 | Partial Approval | MICHEL ABAJAN |
| Deputy Steel/Welding | 6/30/2022 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 8/26/2022 | Partial Approval | THOMAS FINNILA |
| Deputy Steel/Welding | 9/6/2022 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Partial Approval | THOMAS FINNILA |
| Deputy Wood Construction | 10/24/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Corrections Issued | JACK KARGODORIAN |
| Deputy Steel/Welding | 11/1/2022 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 11/3/2022 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 12/19/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 1/12/2023 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 1/13/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/19/2023 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/19/2023 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 1/19/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 2/14/2023 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 2/23/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 2/28/2023 | Partial Approval | JACK KARGODORIAN |
| Underground Mechanical | 3/3/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/7/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 3/10/2023 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 3/16/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 3/20/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 3/29/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/29/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 4/10/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 4/10/2023 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 4/13/2023 | Approved | JACK KARGODORIAN |
| Deck | 5/17/2023 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/17/2023 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 10/20/2023 | Partial Approval | JUAN VALENZUELA |
| Gas Test | 3/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 4/4/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 4/10/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/15/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 5/1/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/1/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/3/2024 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 5/3/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 6/4/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 6/4/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 6/4/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 6/4/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/4/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/4/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/16/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 10/16/2024 | Approved | CHRISTOPHER ROJAS |