4405 S CAMPBELL DR 90066

Certificate Information: 4405 S CAMPBELL DR 90066

Application / Permit
20010-30000-00483
Plan Check / Job No.
B20WL00759
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 1-story Accessory dwelling unit at rear of the lot. All work per IB/P/BC 2017-004 wood frame prescriptive provision. See comments.
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofO Issued on 2/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/13/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 REZA HAGHIGHAT
Corrections Issued 3/9/2020 REZA HAGHIGHAT
Quality Review Completed 3/19/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 5/11/2020 APPLICANT
Plan Check Approved 6/23/2020 REZA HAGHIGHAT
Issued 7/7/2020 APPLICANT
Building Plans Picked Up 7/8/2020 APPLICANT
CofO in Progress 1/12/2021 ENRIQUE MIRELES
CofO in Progress 1/12/2021 ENRIQUE MIRELES
CofO Issued 2/1/2021 VINCENT COTTON
Permit Finaled 2/1/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 4/1/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 4/22/2020 DINAH GARIN
Sewer availability Cleared 4/22/2020 DINAH GARIN
Hydrant and Access approval Cleared 4/23/2020 GILBERT URREA
Green Code Cleared 5/6/2020 RICHARD GARCIA
Construction near power lines Cleared 5/13/2020 RIDWAN HARDY
Low Impact Development Cleared 5/29/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 6/25/2020 DINAH GARIN

Contact Information

Contractor Bems Construction; Lic. No.: 1014009-B 2930 E 5TH ST APT #8      LONG BEACH, CA 90814

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/9/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 7/14/2020 Conditional Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval JUAN VALENZUELA
Green Building Rough 8/21/2020 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 8/21/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 8/26/2020 Corrections Issued DAVID HEINE
PLUMBING-Rough 8/26/2020 Corrections Issued DAVID HEINE
ELECTRICAL-Rough 9/1/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 9/1/2020 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 9/2/2020 Partial Approval DAVID HEINE
Green Building Rough 9/2/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 9/2/2020 Partial Approval DAVID HEINE
Verify Sprinkler Sign Off 9/2/2020 Approved DAVID HEINE
HVAC-Rough 9/4/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/4/2020 Partial Approval JUAN VALENZUELA
Wood Frame 9/4/2020 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 9/9/2020 Approved DAVID HEINE
Green Building Rough 9/9/2020 Approved DAVID HEINE
Insulation 9/9/2020 Approved DAVID HEINE
Interior/Exterior Lathing 9/9/2020 Approved DAVID HEINE
Drywall Nailing 9/11/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 10/16/2020 Approved ENRIQUE MIRELES
Final 10/16/2020 Not Ready for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 10/16/2020 Approved ENRIQUE MIRELES
Green Building Final 10/16/2020 Approved ENRIQUE MIRELES
HVAC-Final 10/16/2020 Approved ENRIQUE MIRELES
PLUMBING-Final 10/16/2020 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 10/16/2020 Not Ready for Inspection ENRIQUE MIRELES
Smoke Detectors 10/16/2020 Approved ENRIQUE MIRELES
Final 12/1/2020 Corrections Issued ENRIQUE MIRELES
Service/Power Release 12/1/2020 Corrections Issued ENRIQUE MIRELES
Final 1/12/2021 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 1/12/2021 Approved ENRIQUE MIRELES