817-819 N SYCAMORE AVE 90038

Certificate Information: 817-819 N SYCAMORE AVE 90038

Application / Permit
20010-30000-00466
Plan Check / Job No.
B20WL00734
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2 story duplex with attached garage.
Permit Issued
Issued on 10/20/2020
Issuing Office
Current Status
CofO Issued on 3/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/12/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 3/10/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 3/18/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 4/29/2020 APPLICANT
Plan Check Approved 10/13/2020 VLADIMIR ARUTYUNYAN
Issued 10/20/2020 APPLICANT
Building Plans Picked Up 12/11/2020 APPLICANT
CofO in Progress 3/7/2022 BRIAN SULLIVAN
Permit Finaled 3/23/2022 DEROLD HAUFF
CofO Issued 3/23/2022 DEROLD HAUFF
Permit Finaled 3/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 4/1/2020 JOHN KIM
Green Code Cleared 4/29/2020 RICHARD GARCIA
Low Impact Development Cleared 6/24/2020 SARAH YOUSSEF
Hydrant and Access approval Cleared 6/25/2020 KURT CORRAL
Address approval Cleared 7/9/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/9/2020 RENZ SORIANO
Permit Cleared 7/9/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 7/9/2020 RENZ SORIANO
Sewer availability Cleared 7/9/2020 RENZ SORIANO

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/15/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/4/2021 Corrections Issued BRIAN SULLIVAN
Underground Mechanical 1/4/2021 Corrections Issued BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 1/5/2021 Approved BRIAN SULLIVAN
Sewer 1/15/2021 Partial Approval BRIAN SULLIVAN
Underground Mechanical 1/15/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2021 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 2/2/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Partial Approval BRIAN SULLIVAN
Green Building Rough 2/2/2021 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Rough 2/2/2021 Approved BRIAN SULLIVAN
METHANE-Subgrade 2/2/2021 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 2/2/2021 Not Ready for Inspection BRIAN SULLIVAN
Deputy Wood Construction 2/19/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 3/1/2021 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval JOSEPH MCGARRY
Insulation 3/2/2021 Partial Approval BRIAN SULLIVAN
Insulation 3/5/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Rough 3/9/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 3/10/2021 Approved BRIAN SULLIVAN
Deputy Wood Construction 3/18/2021 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 3/18/2021 Partial Approval BRIAN SULLIVAN
ELECTRICAL-Rough 3/26/2021 Approved BRIAN SULLIVAN
Shower Pan 3/26/2021 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 4/22/2021 Approved BRIAN SULLIVAN
Green Building Rough 4/22/2021 Approved BRIAN SULLIVAN
HVAC-Rough 4/22/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 4/22/2021 Partial Approval BRIAN SULLIVAN
Shower Pan 4/22/2021 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 4/22/2021 Approved BRIAN SULLIVAN
Drywall Nailing 5/14/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 5/14/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Final 7/22/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Final 7/22/2021 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 7/29/2021 No Access for Inspection RAUL BARAJAS
PLUMBING-Final 8/9/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Final 8/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Pre-Inspection 11/4/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 11/23/2021 Approved BRIAN SULLIVAN
HVAC-Final 11/23/2021 Approved BRIAN SULLIVAN
Service/Power Release 11/23/2021 Not Ready for Inspection BRIAN SULLIVAN
Final 12/2/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 12/2/2021 Approved BRIAN SULLIVAN
Gas Test 12/2/2021 Approved BRIAN SULLIVAN
Green Building Final 12/2/2021 Approved BRIAN SULLIVAN
METHANE-Barrier 12/2/2021 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 12/2/2021 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 12/2/2021 Approved BRIAN SULLIVAN
Final 1/19/2022 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 1/19/2022 Not Ready for Inspection BRIAN SULLIVAN
Final 2/1/2022 Corrections Issued BRIAN SULLIVAN
Service/Power Release 2/1/2022 Approved BRIAN SULLIVAN
Final 3/7/2022 OK to Issue CofO BRIAN SULLIVAN