817-819 N SYCAMORE AVE 90038
Certificate Information: 817-819 N SYCAMORE AVE 90038
- Application / Permit
- 20010-30000-00466
- Plan Check / Job No.
- B20WL00734
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2 story duplex with attached garage.
- Permit Issued
- Issued on 10/20/2020
- Issuing Office
- Current Status
- CofO Issued on 3/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 3/10/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 3/18/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 4/29/2020 | APPLICANT |
| Plan Check Approved | 10/13/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 10/20/2020 | APPLICANT |
| Building Plans Picked Up | 12/11/2020 | APPLICANT |
| CofO in Progress | 3/7/2022 | BRIAN SULLIVAN |
| Permit Finaled | 3/23/2022 | DEROLD HAUFF |
| CofO Issued | 3/23/2022 | DEROLD HAUFF |
| Permit Finaled | 3/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 4/1/2020 | JOHN KIM |
| Green Code | Cleared | 4/29/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 6/24/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 6/25/2020 | KURT CORRAL |
| Address approval | Cleared | 7/9/2020 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2020 | RENZ SORIANO |
| Permit | Cleared | 7/9/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 7/9/2020 | RENZ SORIANO |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/15/2020 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/4/2021 | Corrections Issued | BRIAN SULLIVAN |
| Underground Mechanical | 1/4/2021 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 1/5/2021 | Approved | BRIAN SULLIVAN |
| Sewer | 1/15/2021 | Partial Approval | BRIAN SULLIVAN |
| Underground Mechanical | 1/15/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2021 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/2/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 2/2/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Rough | 2/2/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 2/2/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 2/2/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Wood Construction | 2/19/2021 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/1/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 3/2/2021 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 3/5/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Rough | 3/9/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 3/10/2021 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 3/18/2021 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 3/18/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 3/26/2021 | Approved | BRIAN SULLIVAN |
| Shower Pan | 3/26/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/22/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 4/22/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 4/22/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/22/2021 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 4/22/2021 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 4/22/2021 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 5/14/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/14/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 7/22/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 7/22/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/29/2021 | No Access for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 8/9/2021 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 8/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 11/4/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 11/23/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 11/23/2021 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 11/23/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 12/2/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 12/2/2021 | Approved | BRIAN SULLIVAN |
| Gas Test | 12/2/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 12/2/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Barrier | 12/2/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 12/2/2021 | Corrections Issued | BRIAN SULLIVAN |
| Smoke Detectors | 12/2/2021 | Approved | BRIAN SULLIVAN |
| Final | 1/19/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 1/19/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 2/1/2022 | Corrections Issued | BRIAN SULLIVAN |
| Service/Power Release | 2/1/2022 | Approved | BRIAN SULLIVAN |
| Final | 3/7/2022 | OK to Issue CofO | BRIAN SULLIVAN |