752 N HARTZELL ST 90272

Certificate Information: 752 N HARTZELL ST 90272

Application / Permit
20010-30000-00386
Plan Check / Job No.
B20WL00615
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFR WITH (N) ATTACHED 2-CAR GARAGE & ROOF TRUSSES
Permit Issued
Issued on 7/7/2020
Issuing Office
Current Status
CofO Issued on 7/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/5/2020 APPLICANT
Assigned to Plan Check Engineer 3/5/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 3/9/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 3/16/2020 FELIX FIGUEROA
Green Plans Picked Up 4/24/2020 APPLICANT
Plan Check Approved 6/26/2020 KAMRAN GHOTBI RAVANDI
Issued 7/7/2020 APPLICANT
Building Plans Picked Up 7/8/2020 APPLICANT
CofO in Progress 6/16/2021 JOHN KIDWELL
CofO in Progress 6/29/2021 JOHN KIDWELL
CofO Issued 7/7/2021 VINCENT COTTON
Permit Finaled 7/7/2021 VINCENT COTTON

Permit Application Clearance Information

Trees in Parkway Cleared 4/1/2020 JOHN KIM
Hydrant and Access approval Cleared 4/9/2020 ROBERT DUFF
Green Code Cleared 4/24/2020 RICHARD GARCIA
Low Impact Development Cleared 5/28/2020 JORGE MEJIA LEMUS
Permit Cleared 6/5/2020 DINAH GARIN
Roof/Waste drainage to street Cleared 6/5/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 6/9/2020 DINAH GARIN
Sewer availability Cleared 6/9/2020 DINAH GARIN

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/23/2020 Not Ready for Inspection ROBERT SHELLY
PLUMBING-Rough 7/27/2020 Partial Approval ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 7/30/2020 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 7/31/2020 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/18/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 9/17/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 12/17/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 12/17/2020 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 1/5/2021 Partial Approval JOHN KIDWELL
PLUMBING-Rough 1/7/2021 Approved JOHN KIDWELL
Shower Pan 1/7/2021 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 1/19/2021 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/1/2021 Corrections Issued JOHN KIDWELL
Green Building Rough 2/1/2021 Not Ready for Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 2/1/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 2/2/2021 Approved JOHN KIDWELL
Green Building Rough 2/2/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 2/2/2021 Approved JOHN KIDWELL
Drywall Nailing 2/12/2021 Not Ready for Inspection JOHN KIDWELL
Drywall Nailing 2/16/2021 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/18/2021 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 5/14/2021 Corrections Issued JOHN KIDWELL
Gas Test 5/18/2021 Approved JOHN KIDWELL
PLUMBING-Final 5/18/2021 Approved JOHN KIDWELL
HVAC-Final 5/24/2021 Approved JOHN KIDWELL
ELECTRICAL-Final 6/3/2021 Approved JOHN KIDWELL
Final 6/3/2021 Conditional Approval JOHN KIDWELL
Green Building Final 6/3/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Approved JOHN KIDWELL
Service/Power Release 6/3/2021 Approved JOHN KIDWELL
Smoke Detectors 6/3/2021 Approved JOHN KIDWELL
Final 6/11/2021 OK to Issue CofO JOHN KIDWELL
Final 6/15/2021 OK to Issue CofO JOHN KIDWELL
Service/Power Release 6/25/2021 Not Ready for Inspection JOHN KIDWELL