752 N HARTZELL ST 90272
Certificate Information: 752 N HARTZELL ST 90272
- Application / Permit
- 20010-30000-00386
- Plan Check / Job No.
- B20WL00615
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFR WITH (N) ATTACHED 2-CAR GARAGE & ROOF TRUSSES
- Permit Issued
- Issued on 7/7/2020
- Issuing Office
- Current Status
- CofO Issued on 7/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/5/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 3/9/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 3/16/2020 | FELIX FIGUEROA |
| Green Plans Picked Up | 4/24/2020 | APPLICANT |
| Plan Check Approved | 6/26/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 7/7/2020 | APPLICANT |
| Building Plans Picked Up | 7/8/2020 | APPLICANT |
| CofO in Progress | 6/16/2021 | JOHN KIDWELL |
| CofO in Progress | 6/29/2021 | JOHN KIDWELL |
| CofO Issued | 7/7/2021 | VINCENT COTTON |
| Permit Finaled | 7/7/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 4/1/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/9/2020 | ROBERT DUFF |
| Green Code | Cleared | 4/24/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 5/28/2020 | JORGE MEJIA LEMUS |
| Permit | Cleared | 6/5/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 6/5/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2020 | DINAH GARIN |
| Sewer availability | Cleared | 6/9/2020 | DINAH GARIN |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/23/2020 | Not Ready for Inspection | ROBERT SHELLY |
| PLUMBING-Rough | 7/27/2020 | Partial Approval | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 7/30/2020 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/31/2020 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 1/5/2021 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 1/7/2021 | Approved | JOHN KIDWELL |
| Shower Pan | 1/7/2021 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/19/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/1/2021 | Corrections Issued | JOHN KIDWELL |
| Green Building Rough | 2/1/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/1/2021 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/2/2021 | Approved | JOHN KIDWELL |
| Green Building Rough | 2/2/2021 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 2/2/2021 | Approved | JOHN KIDWELL |
| Drywall Nailing | 2/12/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Drywall Nailing | 2/16/2021 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/18/2021 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 5/14/2021 | Corrections Issued | JOHN KIDWELL |
| Gas Test | 5/18/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 5/18/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 5/24/2021 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 6/3/2021 | Approved | JOHN KIDWELL |
| Final | 6/3/2021 | Conditional Approval | JOHN KIDWELL |
| Green Building Final | 6/3/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/3/2021 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 6/3/2021 | Approved | JOHN KIDWELL |
| Smoke Detectors | 6/3/2021 | Approved | JOHN KIDWELL |
| Final | 6/11/2021 | OK to Issue CofO | JOHN KIDWELL |
| Final | 6/15/2021 | OK to Issue CofO | JOHN KIDWELL |
| Service/Power Release | 6/25/2021 | Not Ready for Inspection | JOHN KIDWELL |