11531 W ORUM ROAD 90049

Certificate Information: 11531 W ORUM ROAD 90049

Application / Permit
20010-30000-00375
Plan Check / Job No.
B20WL00607
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW POOL PAVILLION AND MECHANICAL ROOM BELOW AND ATTACHED DECK.
Permit Issued
Issued on 9/11/2020
Issuing Office
Current Status
CofO Issued on 5/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 3/12/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 3/18/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 3/27/2020 CORA JOHNSON
Applicant returned to address corrections 5/15/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 8/21/2020 APPLICANT
Plan Check Approved 9/10/2020 KAMRAN GHOTBI RAVANDI
Issued 9/11/2020 APPLICANT
Building Plans Picked Up 9/14/2020 APPLICANT
CofO in Progress 5/5/2024 CARLOS MATAMOROS
Permit Finaled 5/20/2024 DANIEL ORRANTE
CofO Issued 5/20/2024 DANIEL ORRANTE
Permit Finaled 5/20/2024 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 4/7/2020 DINAH GARIN
Miscellaneous Cleared 4/9/2020 DENZEL HENDERSON
ZI Cleared 4/9/2020 DENZEL HENDERSON
Hydrant and Access approval Cleared 4/14/2020 GEORGE SUCHAND
Low Impact Development Cleared 7/7/2020 ROBIN YAMADA
Eng Process Fee Ord 176,300 Cleared 7/30/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 8/4/2020 DINAH GARIN
Green Code Cleared 8/21/2020 RICHARD GARCIA
Excavation more than 5-ft deep Cleared 9/10/2020 CALOSHA APPROVED

Contact Information

Contractor Walker Workshop; Lic. No.: 954191-B 5574 WASHINGTON BLVD      LOS ANGELES, CA 90016

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/2/2021 Not Ready for Inspection CARLOS MATAMOROS
Piling/Pier/Caisson 2/4/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 3/31/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 4/28/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/11/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/24/2021 Partial Approval CARLOS MATAMOROS
Piling/Pier/Caisson 5/24/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 8/19/2021 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 8/24/2021 Conditional Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 10/22/2021 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/22/2021 Approved CARLOS MATAMOROS
Reinforced Concrete Frame 11/10/2021 Partial Approval CARLOS MATAMOROS
Underground Mechanical 12/3/2021 Approved CARLOS MATAMOROS
Deck 12/15/2021 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 12/15/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 12/15/2021 Partial Approval CARLOS MATAMOROS
Pool Piping 12/15/2021 Approved CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 12/15/2021 Partial Approval CARLOS MATAMOROS
Deck 1/5/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 1/27/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 1/27/2022 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 1/27/2022 Partial Approval CARLOS MATAMOROS
Sewer 1/27/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 2/9/2022 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 2/9/2022 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 4/6/2023 Approved CARLOS MATAMOROS
HVAC-Rough 4/6/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/6/2023 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 5/10/2023 Approved CARLOS MATAMOROS
Drywall Nailing 5/10/2023 Approved CARLOS MATAMOROS
Green Building Rough 5/10/2023 Approved CARLOS MATAMOROS
Shower Pan 5/17/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/31/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Final 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Concrete Frame 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Masonry Frame 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/14/2023 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/14/2023 Not Ready for Inspection CARLOS MATAMOROS
Final 1/26/2024 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 1/26/2024 Approved CARLOS MATAMOROS
Reinforced Concrete Frame 1/26/2024 Approved CARLOS MATAMOROS
Reinforced Masonry Frame 1/26/2024 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 1/26/2024 SGSOV Approved CARLOS MATAMOROS
Service/Power Release 1/26/2024 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 1/26/2024 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/26/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Final 5/3/2024 Approved CARLOS MATAMOROS
Final 5/3/2024 OK to Issue CofO CARLOS MATAMOROS
HVAC-Final 5/3/2024 Approved CARLOS MATAMOROS
PLUMBING-Final 5/3/2024 Approved CARLOS MATAMOROS
Service/Power Release 5/3/2024 Approved CARLOS MATAMOROS