3630-3632 S BEETHOVEN ST 90066

Certificate Information: 3630-3632 S BEETHOVEN ST 90066

Application / Permit
20010-30000-00357
Plan Check / Job No.
B20WL00575
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(n) 2-story duplex. Both w/attached 2-car garages & roof trusses.
Permit Issued
Issued on 7/8/2020
Issuing Office
Current Status
CofO Issued on 8/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 3/2/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 3/9/2020 FELIX FIGUEROA
Green Plans Picked Up 4/3/2020 APPLICANT
Plan Check Approved 7/8/2020 KAMRAN GHOTBI RAVANDI
Issued 7/8/2020 APPLICANT
Building Plans Picked Up 7/9/2020 APPLICANT
CofO in Progress 7/20/2021 ENRIQUE MIRELES
Permit Finaled 8/9/2021 VINCENT COTTON
CofO Issued 8/9/2021 VINCENT COTTON
Permit Finaled 8/9/2021 VINCENT COTTON

Permit Application Clearance Information

Green Code Cleared 4/1/2020 DONALD CRICHLOW
Trees in Parkway Cleared 4/14/2020 JOHN KIM
Hydrant and Access approval Cleared 4/22/2020 KURT CORRAL
Address approval Cleared 5/20/2020 ANTHONY MAINEZ
Permit Cleared 5/20/2020 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/21/2020 ANTHONY MAINEZ
Sewer availability Cleared 5/21/2020 ANTHONY MAINEZ
Construction near power lines Cleared 5/28/2020 OSCAR CASTRO
Specific Plan Cleared 6/2/2020 FREDDY GARCIA
Low Impact Development Cleared 6/3/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/16/2020 ANTHONY MAINEZ
Highway dedication Cleared 6/22/2020 RAYMOND MUGAMBWA

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: C23971 52 DAWNWOOD      LADERA RANCH, CA 92694
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2020 Partial Approval DAVID HEINE
Excavation/Setback/Form/Re-Bar 9/2/2020 Approved DAVID HEINE
Footing/Foundation/Slab 9/2/2020 Partial Approval DAVID HEINE
Deputy Reinf. Concrete 9/3/2020 Conditional Approval JOHNNY MIRANDA
Sewer 9/30/2020 Approved ENRIQUE MIRELES
Underground Mechanical 9/30/2020 Approved ENRIQUE MIRELES
PLUMBING-Rough 10/1/2020 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 10/1/2020 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Partial Approval ENRIQUE MIRELES
Deputy Wood Construction 10/22/2020 Approved ENRIQUE MIRELES
Deputy Wood Construction 10/26/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Approved ENRIQUE MIRELES
Drywall Nailing 11/24/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 11/24/2020 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 1/7/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 1/7/2021 Partial Approval ENRIQUE MIRELES
HVAC-Rough 1/13/2021 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/20/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/26/2021 Approved ENRIQUE MIRELES
Green Building Rough 1/26/2021 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 1/26/2021 Approved ENRIQUE MIRELES
Insulation 2/1/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/1/2021 Approved ENRIQUE MIRELES
Drywall Nailing 2/10/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/10/2021 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 2/10/2021 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 2/12/2021 Approved ENRIQUE MIRELES
Gas Test 4/13/2021 Approved ENRIQUE MIRELES
Verify Rec and Parks Fee Memo 4/13/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 4/26/2021 Approved ENRIQUE MIRELES
Service/Power Release 4/26/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 7/20/2021 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 7/20/2021 Approved ENRIQUE MIRELES
Green Building Final 7/20/2021 Approved ENRIQUE MIRELES
HVAC-Final 7/20/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 7/20/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 7/20/2021 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 7/20/2021 Approved ENRIQUE MIRELES
Smoke Detectors 7/20/2021 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 7/21/2021 Approved ENRIQUE MIRELES
Final 7/21/2021 OK to Issue CofO ENRIQUE MIRELES