859-861 N VISTA ST 90046
Certificate Information: 859-861 N VISTA ST 90046
- Application / Permit
- 20010-30000-00340
- Plan Check / Job No.
- B20WL00546
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (n) 2-story duplex w/ attached garages and roof trusses
- Permit Issued
- Issued on 7/9/2020
- Issuing Office
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/26/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 3/4/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 3/13/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 4/24/2020 | APPLICANT |
| Plan Check Approved | 7/1/2020 | VLADIMIR ARUTYUNYAN |
| Issued | 7/9/2020 | APPLICANT |
| Building Plans Picked Up | 7/16/2020 | APPLICANT |
| CofO in Progress | 4/30/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/11/2021 | DEROLD HAUFF |
| CofO Issued | 5/11/2021 | DEROLD HAUFF |
| Permit Finaled | 5/11/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 3/13/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 4/14/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 4/24/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 5/28/2020 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 6/8/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2020 | JUAN ASHTON |
| Permit | Cleared | 6/8/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 6/8/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 6/8/2020 | JUAN ASHTON |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 8/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Reinf. Concrete | 8/18/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 8/18/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/18/2020 | Approved | CHRIS CHRISTENSEN |
| Sewer | 9/1/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/16/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Insulation | 10/16/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 11/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/10/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/17/2020 | Corrections Issued | MICHAEL PELHAM |
| ELECTRICAL-Rough | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 11/24/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/24/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 11/24/2020 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/1/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 12/1/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 12/1/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Insulation | 12/8/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 12/14/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/16/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/16/2020 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/15/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 3/15/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 3/15/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/15/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/22/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/22/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Rough | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2021 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 3/31/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 3/31/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/31/2021 | SGSOV Approved | CHRIS CHRISTENSEN |