859-861 N VISTA ST 90046

Certificate Information: 859-861 N VISTA ST 90046

Application / Permit
20010-30000-00340
Plan Check / Job No.
B20WL00546
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(n) 2-story duplex w/ attached garages and roof trusses
Permit Issued
Issued on 7/9/2020
Issuing Office
Current Status
CofO Issued on 5/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2020 APPLICANT
Assigned to Plan Check Engineer 2/26/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 3/4/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 3/13/2020 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 4/24/2020 APPLICANT
Plan Check Approved 7/1/2020 VLADIMIR ARUTYUNYAN
Issued 7/9/2020 APPLICANT
Building Plans Picked Up 7/16/2020 APPLICANT
CofO in Progress 4/30/2021 CHRIS CHRISTENSEN
Permit Finaled 5/11/2021 DEROLD HAUFF
CofO Issued 5/11/2021 DEROLD HAUFF
Permit Finaled 5/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 3/13/2020 JOHN KIM
Hydrant and Access approval Cleared 4/14/2020 GEORGE SUCHAND
Green Code Cleared 4/24/2020 RICHARD GARCIA
Low Impact Development Cleared 5/28/2020 JORGE MEJIA LEMUS
Address approval Cleared 6/8/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 6/8/2020 JUAN ASHTON
Permit Cleared 6/8/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 6/8/2020 JUAN ASHTON
Sewer availability Cleared 6/8/2020 JUAN ASHTON

Contact Information

Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/10/2020 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 8/10/2020 Partial Approval CHRIS CHRISTENSEN
Deputy Reinf. Concrete 8/18/2020 Conditional Approval CHRIS CHRISTENSEN
Deputy Wood Construction 8/18/2020 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 8/18/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/18/2020 Approved CHRIS CHRISTENSEN
Sewer 9/1/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 10/16/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Conditional Approval CHRIS CHRISTENSEN
Insulation 10/16/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 11/10/2020 Approved CHRIS CHRISTENSEN
Insulation 11/10/2020 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 11/10/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 11/17/2020 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 11/24/2020 Approved CHRIS CHRISTENSEN
Gas Test 11/24/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/24/2020 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 11/24/2020 Approved CHRIS CHRISTENSEN
Shower Pan 11/24/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 12/1/2020 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 12/1/2020 Corrections Issued CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 12/1/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 12/8/2020 Partial Approval CHRIS CHRISTENSEN
Insulation 12/14/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/16/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 12/16/2020 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 3/15/2021 Approved CHRIS CHRISTENSEN
Gas Test 3/15/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 3/15/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/15/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/22/2021 Approved CHRIS CHRISTENSEN
Final 3/22/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 3/22/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 3/22/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 3/22/2021 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 3/22/2021 Approved CHRIS CHRISTENSEN
Smoke Detectors 3/22/2021 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 3/22/2021 Approved CHRIS CHRISTENSEN
Final 3/31/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 3/31/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Approved CHRIS CHRISTENSEN