9620 W CEDARBROOK DR 90210

Certificate Information: 9620 W CEDARBROOK DR 90210

Application / Permit
20010-30000-00246
Plan Check / Job No.
B20WL00357
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
New detached (2) story Accessory Living Quarters.Fully Sprinklered
Permit Issued
Issued on 7/6/2020
Issuing Office
Current Status
CofO Issued on 8/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2020 APPLICANT
Assigned to Plan Check Engineer 2/27/2020 SAM CHANG
Corrections Issued 3/16/2020 SAMUEL GONZALEZ
Quality Review Completed 3/17/2020 LAWRENCE QUIRANTE
Building Plans Picked Up 3/18/2020 APPLICANT
Green Plans Picked Up 4/16/2020 APPLICANT
Plan Check Approved 6/16/2020 SAMUEL GONZALEZ
Issued 7/6/2020 APPLICANT
CofO in Progress 7/10/2021 RAUL BARAJAS
Permit Finaled 8/13/2021 DEROLD HAUFF
CofO Issued 8/13/2021 DEROLD HAUFF
Permit Finaled 8/13/2021 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/1/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 4/1/2020 DINAH GARIN
BHO/Hillside ordinance Cleared 4/1/2020 DINAH GARIN
ZI Cleared 4/2/2020 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 4/9/2020 DINAH GARIN
Sewer availability Cleared 4/9/2020 DINAH GARIN
Green Code Cleared 4/15/2020 RICHARD GARCIA
Hydrant and Access approval Cleared 4/28/2020 KURT CORRAL
Low Impact Development Cleared 4/28/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/30/2020 DINAH GARIN
Address approval Cleared 5/4/2020 DINAH GARIN
Grading Pre-Inspection Cleared 5/29/2020 SAMUEL GONZALEZ

Contact Information

Contractor Williams Craig R Construction Inc; Lic. No.: 479539-B 9100 WILSHIRE BLVD   STE 503E    BEVERLY HILLS, CA 90212
Engineer Ilasin,, John Lacebal; Lic. No.: C67469 1011 OARFISH LN      OXNARD, CA 93035

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/15/2020 Approved JOSEPH MCGARRY
Deputy Reinf. Concrete 7/22/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 7/27/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 7/31/2020 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 8/3/2020 Partial Approval RAUL BARAJAS
Deputy Reinf. Concrete 8/4/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Reinf. Concrete 8/6/2020 Conditional Approval RAUL BARAJAS
Footing/Foundation/Slab 8/6/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval RAUL BARAJAS
Green Building Rough 8/14/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/14/2020 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval RAUL BARAJAS
Green Building Rough 8/19/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/19/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 8/26/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Partial Approval RAUL BARAJAS
Green Building Rough 8/31/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/31/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Steel/Welding 10/1/2020 Conditional Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Approved RAUL BARAJAS
Green Building Rough 10/1/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 10/1/2020 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 10/8/2020 Partial Approval COREY HUPP
Underground Mechanical 10/8/2020 Partial Approval COREY HUPP
ELECTRICAL-Rough 10/20/2020 Approved RAUL BARAJAS
HVAC-Rough 10/20/2020 Approved RAUL BARAJAS
BUILDING-Rough-Frame 11/2/2020 Approved RAUL BARAJAS
Green Building Rough 11/2/2020 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 11/2/2020 Approved RAUL BARAJAS
Drywall Nailing 11/10/2020 Approved DONALD CRICHLOW
Interior/Exterior Lathing 11/10/2020 Approved DONALD CRICHLOW
ELECTRICAL-Final 3/5/2021 Approved RAUL BARAJAS
HVAC-Final 3/5/2021 Approved RAUL BARAJAS
PLUMBING-Final 3/5/2021 Approved RAUL BARAJAS
Final 3/11/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 3/11/2021 Approved RAUL BARAJAS
Green Building Final 3/11/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 3/11/2021 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 3/11/2021 Approved RAUL BARAJAS
Final 4/9/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Final 4/9/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved RAUL BARAJAS
Service/Power Release 4/9/2021 Not Ready for Inspection RAUL BARAJAS
Final 4/27/2021 Corrections Issued RAUL BARAJAS
Service/Power Release 4/27/2021 Not Required RAUL BARAJAS
Final 7/6/2021 Not Ready for Inspection RAUL BARAJAS
Final 7/9/2021 OK to Issue CofO RAUL BARAJAS