12401 N RIDGELINE RD PLAN #6 91326
Certificate Information: 12401 N RIDGELINE RD PLAN #6 91326
- Application / Permit
- 20010-20001-03050
- Plan Check / Job No.
- B21VN00495
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR 20010-20000-03050 TO CONVERT GARAGE INTO SALES OFFICE
- Permit Issued
- Issued on 6/1/2021
- Issuing Office
- Current Status
- Permit Finaled on 7/20/2022
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 1/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/9/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/9/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 2/23/2021 | APPLICANT |
| Plan Check Approved | 5/19/2021 | NILOOFAR MEHRAIN |
| Issued | 6/1/2021 | APPLICANT |
| Permit Finaled | 7/19/2022 | JEFFREY FULTON |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/3/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 3/3/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 3/3/2021 | DANG NGUYEN |
| ZA Case | Cleared | 3/3/2021 | DANG NGUYEN |
| ZA Case | Cleared | 3/3/2021 | DANG NGUYEN |
| ZI | Cleared | 3/3/2021 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/22/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/22/2021 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 4/27/2021 | NORLITO MEDRANO |
| "T" removal | Cleared | 5/19/2021 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 5/19/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 7/20/2021 | Approved | JEFFREY FULTON |
| Insulation | 7/20/2021 | Approved | JEFFREY FULTON |
| Wood Frame | 7/20/2021 | Approved | JEFFREY FULTON |
| Drywall Nailing | 7/26/2021 | Approved | JEFFREY FULTON |
| Final | 11/5/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Smoke Detectors | 11/5/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 11/10/2021 | Conditional Approval | JEFFREY FULTON |
| Smoke Detectors | 11/10/2021 | Approved | JEFFREY FULTON |
| Special/Order Compliance | 4/13/2022 | Partial Inspection | JEFFREY FULTON |
| Final | 6/27/2022 | Conditional Approval | JEFFREY FULTON |
| Final | 7/19/2022 | Permit Finaled | JEFFREY FULTON |