5932 E ECHO ST 90042

Certificate Information: 5932 E ECHO ST 90042

Application / Permit
20010-20001-00182
Plan Check / Job No.
B24VN06565
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO PERMIT# 20010-20000-00182 TO REVISE SIZE OF THE BUILDING TO NEW 10'-0" x 24'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 7/26/2024
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2024 APPLICANT
Assigned to Plan Check Engineer 5/17/2024 SARKIS HARABEDIAN
Corrections Issued 5/22/2024 SARKIS HARABEDIAN
Building Plans Picked Up 6/7/2024 APPLICANT
Plan Check Approved 6/21/2024 SARKIS HARABEDIAN
Issued 7/26/2024 APPLICANT
Permit Finaled 5/12/2025 LILIANA PORTILLO

Permit Application Clearance Information

Miscellaneous Cleared 6/10/2024 YINGSHI HUANG
HPOZ Cleared 6/12/2024 NATHALY DE LA PAZ
Specific Plan Cleared 6/18/2024 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,
Contractor Tun J G Construction Inc; Lic. No.: 1059792-B 2055 WEST JEFFERSON BLVD      LOS ANGELES, CA 90018

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/13/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 8/13/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 9/6/2024 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 9/6/2024 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 10/4/2024 Approved LILIANA PORTILLO
PLUMBING-Rough 10/4/2024 Approved LILIANA PORTILLO
Sewer 10/4/2024 Approved LILIANA PORTILLO
Underground Mechanical 10/4/2024 Approved LILIANA PORTILLO
HVAC-Rough 10/17/2024 Approved LILIANA PORTILLO
Underground Mechanical 10/17/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/6/2024 Corrections Issued LILIANA PORTILLO
Green Building Rough 11/6/2024 Approved LILIANA PORTILLO
Insulation 11/21/2024 Approved ANTHONY RAMOS
Drywall Nailing 11/26/2024 Approved LILIANA PORTILLO
Shower Pan 12/3/2024 Approved ANTHONY RAMOS
BUILDING-Rough-Frame 1/16/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 1/16/2025 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 1/30/2025 Approved LILIANA PORTILLO
Final 1/30/2025 Corrections Issued LILIANA PORTILLO
Final 2/6/2025 Not Ready for Inspection LILIANA PORTILLO
Final 5/12/2025 Permit Finaled LILIANA PORTILLO