18052 W PARTHENIA ST 91325

Certificate Information: 18052 W PARTHENIA ST 91325

Application / Permit
20010-20000-05141
Plan Check / Job No.
B20VN16836
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 57'-6" X 27'-4" (2) STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGOUT
Permit Issued
Issued on 7/9/2021
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 SELLA BENYAMIN
Corrections Issued 1/26/2021 SELLA BENYAMIN
Quality Review Completed 1/29/2021 STEVEN KIM
Building Plans Picked Up 2/2/2021 APPLICANT
Plan Check Approved 7/9/2021 SELLA BENYAMIN
Issued 7/9/2021 APPLICANT
CofO in Progress 9/26/2022 JAVIER RAMOS JR
Permit Finaled 10/29/2022 MICHAEL SMITH
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/29/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/8/2021 GABRIEL ROBLES
Sewer availability Cleared 2/8/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 3/8/2021 MATTHEW CRAIG
Low Impact Development Cleared 6/30/2021 TA ANH
Roof/Waste drainage to street Cleared 7/1/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/5/2021 Corrections Issued MARK JOHNSON
Excavation/Setback/Form/Re-Bar 11/10/2021 Approved MARK JOHNSON
Footing/Foundation/Slab 11/10/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 11/23/2021 Partial Approval MARK JOHNSON
Underground Mechanical 11/23/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 12/13/2021 Partial Approval MARK JOHNSON
Deputy Other (see comments) 12/14/2021 No Access for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Approved MARK JOHNSON
Pre-Inspection 1/21/2022 Partial Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval RAUL OLAGI
Pre-Inspection 1/25/2022 Approved MICHAEL TEMPLE
HVAC-Rough 2/1/2022 Approved RAUL OLAGI
PLUMBING-Rough 2/1/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 2/22/2022 Not Ready for Inspection MICHAEL TEMPLE
ELECTRICAL-Rough 2/22/2022 Corrections Issued MICHAEL TEMPLE
Green Building Rough 2/22/2022 Not Ready for Inspection MICHAEL TEMPLE
Verify Sprinkler Sign Off 2/22/2022 Not Ready for Inspection MICHAEL TEMPLE
BUILDING-Rough-Frame 2/28/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 2/28/2022 Approved RAUL OLAGI
Green Building Rough 2/28/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 2/28/2022 Partial Approval RAUL OLAGI
Shower Pan 2/28/2022 Approved RAUL OLAGI
Verify Sprinkler Sign Off 2/28/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/7/2022 Approved RAUL OLAGI
Insulation 3/7/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 3/7/2022 Not Ready for Inspection RAUL OLAGI
Drywall Nailing 3/16/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 3/16/2022 Approved RAUL OLAGI
Sewer 6/8/2022 Approved JAVIER RAMOS JR
Underground Mechanical 6/8/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/20/2022 Corrections Issued JAVIER RAMOS JR
Final 7/20/2022 Corrections Issued JAVIER RAMOS JR
Gas Test 7/20/2022 Approved JAVIER RAMOS JR
Green Building Final 7/20/2022 Approved JAVIER RAMOS JR
HVAC-Final 7/20/2022 Approved JAVIER RAMOS JR
PLUMBING-Final 7/20/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 7/20/2022 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 7/20/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 8/12/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 8/12/2022 Corrections Issued JAVIER RAMOS JR
Final 9/26/2022 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 9/26/2022 Approved JAVIER RAMOS JR