20446 W SEPTO ST 91311

Certificate Information: 20446 W SEPTO ST 91311

Application / Permit
20010-20000-05135
Plan Check / Job No.
B20VN16808
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 55' X 15' DETACHED ACCESSORY DWELLING UNIT AS PER 65852.2(e)(1)(B) , ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/31/2021
Issuing Office
Current Status
Issued on 8/31/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/12/2021 RARES BODEA
Corrections Issued 1/12/2021 RARES BODEA
Building Plans Picked Up 1/13/2021 APPLICANT
Plan Check Approved 8/17/2021 RARES BODEA
Issued 8/31/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/13/2021 ADRIAN CASTRO
Sewer availability Cleared 1/14/2021 ADRIAN CASTRO
Construction near power lines Cleared 3/31/2021 RIDWAN HARDY
Low Impact Development Cleared 6/17/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/12/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 8/4/2021 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 8/17/2021 ABDULLAH SADOZAI

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/15/2022 Approved JEFFREY PARD
Sewer 2/15/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 3/1/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 7/29/2022 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 12/29/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 12/29/2022 Approved DAVID SCANTLIN
Green Building Rough 12/29/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 12/29/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 12/29/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 12/29/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 1/13/2023 Partial Inspection JUSTIN HAWLEY
Green Building Rough 1/13/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/13/2023 Partial Approval JUSTIN HAWLEY
Shower Pan 1/13/2023 Approved JUSTIN HAWLEY
Insulation 10/5/2023 Approved DAVID SCANTLIN
Drywall Nailing 11/17/2023 Approved JOHN KIDWELL
Green Building Rough 11/17/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/17/2023 Partial Approval JOHN KIDWELL
Verify Sprinkler Sign Off 11/17/2023 Approved JOHN KIDWELL