12746 W MILBANK ST 91604
Certificate Information: 12746 W MILBANK ST 91604
- Application / Permit
- 20010-20000-05119
- Plan Check / Job No.
- B20VN16778
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSROY DWELLING UNIT & 2 PERGOLAS & COVERED PATIO ( 84'-10"X30'-0")
- Permit Issued
- Issued on 6/29/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 1/9/2021 | MOHAMMAD ESMAILI |
| Quality Review Completed | 1/12/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/13/2021 | APPLICANT |
| Plan Check Approved | 6/2/2021 | MOHAMMAD ESMAILI |
| Issued | 6/29/2021 | APPLICANT |
| CofO in Progress | 10/18/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 10/18/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/19/2021 | GABRIEL ROBLES |
| ZA Case | Cleared | 1/19/2021 | MIGUEL GAMBOA |
| ZI | Cleared | 1/19/2021 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 2/23/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 4/20/2021 | MARTIN FRAGOSO |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/18/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Custom Pro Tile & Stone Inc; Lic. No.: 987695-B | 13277 OATMAN DR RANCHO CUCAMONGA, CA 91739 |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/17/2021 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 8/26/2021 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/26/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 8/26/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/6/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 10/6/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 10/6/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 10/8/2021 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/4/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/2/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/2/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 12/2/2021 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 12/2/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/15/2021 | Approved | ASHLEY THOMPSON |
| Green Building Rough | 12/15/2021 | Approved | ASHLEY THOMPSON |
| Insulation | 12/15/2021 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/15/2021 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 1/4/2022 | Approved | JACK KARGODORIAN |
| Sewer | 1/11/2022 | Corrections Issued | CALEB MEISTER |
| Shower Pan | 1/11/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 1/13/2022 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 1/13/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/20/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/20/2022 | Partial Approval | ARAM AVEDISIAN |
| Final | 8/24/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 8/24/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/24/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/24/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 9/29/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/29/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 10/7/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/7/2022 | Approved | CHRISTOPHE COCHRAN |