12746 W MILBANK ST 91604

Certificate Information: 12746 W MILBANK ST 91604

Application / Permit
20010-20000-05119
Plan Check / Job No.
B20VN16778
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ACCESSROY DWELLING UNIT & 2 PERGOLAS & COVERED PATIO ( 84'-10"X30'-0")
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
CofO Issued on 10/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2021 MOHAMMAD ESMAILI
Corrections Issued 1/9/2021 MOHAMMAD ESMAILI
Quality Review Completed 1/12/2021 OMID HEDAYAT
Building Plans Picked Up 1/13/2021 APPLICANT
Plan Check Approved 6/2/2021 MOHAMMAD ESMAILI
Issued 6/29/2021 APPLICANT
CofO in Progress 10/18/2022 CHRISTOPHE COCHRAN
CofO in Progress 10/18/2022 CHRISTOPHE COCHRAN
Permit Finaled 10/22/2022 MICHAEL SMITH
CofO Issued 10/22/2022 MICHAEL SMITH
Permit Finaled 10/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/14/2021 GABRIEL ROBLES
Sewer availability Cleared 1/19/2021 GABRIEL ROBLES
ZA Case Cleared 1/19/2021 MIGUEL GAMBOA
ZI Cleared 1/19/2021 MIGUEL GAMBOA
Hydrant and Access approval Cleared 2/23/2021 KURT CORRAL
Low Impact Development Cleared 4/20/2021 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 5/11/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 5/18/2021 ADRIAN CASTRO

Contact Information

Contractor Custom Pro Tile & Stone Inc; Lic. No.: 987695-B 13277 OATMAN DR      RANCHO CUCAMONGA, CA 91739
Engineer Nohroodi,, Nader Gholi; Lic. No.: C36971 7389 PERIGORD CT      TUJUNGA, CA 91042

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 8/26/2021 Approved ARAM AVEDISIAN
Footing/Foundation/Slab 8/26/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 8/26/2021 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 10/6/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 10/6/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 10/6/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Deputy Wood Construction 10/8/2021 Approved MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/4/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 11/4/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/2/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 12/2/2021 Approved ARAM AVEDISIAN
HVAC-Rough 12/2/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 12/2/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/15/2021 Approved ASHLEY THOMPSON
Green Building Rough 12/15/2021 Approved ASHLEY THOMPSON
Insulation 12/15/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 12/15/2021 Partial Approval ASHLEY THOMPSON
Drywall Nailing 1/4/2022 Approved JACK KARGODORIAN
Sewer 1/11/2022 Corrections Issued CALEB MEISTER
Shower Pan 1/11/2022 Approved CALEB MEISTER
PLUMBING-Rough 1/13/2022 Corrections Issued ARAM AVEDISIAN
Sewer 1/13/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/20/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 1/20/2022 Partial Approval ARAM AVEDISIAN
Final 8/24/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 8/24/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/24/2022 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 8/24/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 8/24/2022 Approved CHRISTOPHE COCHRAN
Final 9/29/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 9/29/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 10/7/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 10/7/2022 Approved CHRISTOPHE COCHRAN