14530 W HESBY ST 91403

Certificate Information: 14530 W HESBY ST 91403

Application / Permit
20010-20000-05117
Plan Check / Job No.
B20VN16768
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL; REMOVE DWELLING EXCEPT FOR 15 LINEAR FEET OF WALL ON WEST SIDE OF WALL; ADD NEW 40' X 80'-10" NEW SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FRIE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/7/2021
Issuing Office
Current Status
CofO Issued on 1/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 SELLA BENYAMIN
Corrections Issued 1/25/2021 SELLA BENYAMIN
Quality Review Completed 1/27/2021 STEVEN KIM
Plan Check Approved 6/8/2021 SELLA BENYAMIN
Plan Check Approved 7/2/2021 SELLA BENYAMIN
Issued 7/7/2021 APPLICANT
Building Plans Picked Up 7/8/2021 APPLICANT
CofO in Progress 10/25/2022 THOMAS FINNILA
CofO Issued 1/17/2023 MICHAEL SMITH
Permit Finaled 1/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Permit Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/18/2021 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 3/15/2021 MATTHEW CRAIG
ZI Cleared 3/15/2021 DANG NGUYEN
Trees in Parkway Cleared 3/31/2021 JOHN KIM
Low Impact Development Cleared 5/25/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/1/2021 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/9/2021 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 7/9/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 7/9/2021 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/20/2021 Approved DANIEL DREW
PLUMBING-Rough 8/26/2021 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 9/7/2021 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 9/7/2021 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/29/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Corrections Issued JACK KARGODORIAN
Green Building Rough 11/29/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval CHRISTOPHE COCHRAN
HVAC-Rough 12/9/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/16/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 12/16/2021 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 12/16/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 12/16/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 12/16/2021 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Rough 12/27/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 12/28/2021 Corrections Issued JACK KARGODORIAN
Gas Test 12/28/2021 Approved JACK KARGODORIAN
Green Building Rough 12/28/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 12/28/2021 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 1/4/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/27/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 1/27/2022 Approved JACK KARGODORIAN
Insulation 2/4/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/4/2022 Partial Approval JACK KARGODORIAN
Shower Pan 2/10/2022 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 2/17/2022 Approved JACK KARGODORIAN
Drywall Nailing 2/22/2022 Partial Approval JACK KARGODORIAN
Drywall Nailing 2/28/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/2/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 8/18/2022 Not Ready for Inspection JOHN HAYES
Final 8/18/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 8/18/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 8/18/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 8/18/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 8/18/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/18/2022 SGSOV Not Ready JOHN HAYES
Service/Power Release 8/18/2022 Not Ready for Inspection JOHN HAYES
Smoke Detectors 8/18/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 9/16/2022 Approved JACK KARGODORIAN
Final 9/16/2022 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 9/16/2022 Approved JACK KARGODORIAN
Green Building Final 9/16/2022 Approved JACK KARGODORIAN
HVAC-Final 9/16/2022 Approved JACK KARGODORIAN
PLUMBING-Final 9/16/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 9/16/2022 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 9/16/2022 Approved JACK KARGODORIAN
Final 9/21/2022 Corrections Issued JACK KARGODORIAN
Service/Power Release 9/21/2022 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 9/22/2022 Approved JACK KARGODORIAN
Service/Power Release 9/22/2022 Not Ready for Inspection JACK KARGODORIAN
Final 10/24/2022 OK to Issue CofO THOMAS FINNILA