12342 W SARAH ST 91604
Certificate Information: 12342 W SARAH ST 91604
- Application / Permit
- 20010-20000-05109
- Plan Check / Job No.
- B20VN16735
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 61'-2" X 47'-10" (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | SELLA BENYAMIN |
| Corrections Issued | 1/25/2021 | SELLA BENYAMIN |
| Quality Review Completed | 1/27/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/29/2021 | APPLICANT |
| Plan Check Approved | 4/30/2021 | SELLA BENYAMIN |
| Issued | 4/30/2021 | APPLICANT |
| CofO in Progress | 6/29/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/5/2022 | DEROLD HAUFF |
| CofO Issued | 8/5/2022 | DEROLD HAUFF |
| Permit Finaled | 8/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Permit | Cleared | 2/4/2021 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/9/2021 | MARKOS PEREZ-BRAN |
| Trees in Parkway | Cleared | 2/25/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 3/16/2021 | MATTHEW CRAIG |
| ZI | Cleared | 3/19/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 4/20/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/21/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/7/2021 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/25/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/29/2021 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 7/1/2021 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2021 | Partial Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2021 | Conditional Approval | ARAM AVEDISIAN |
| Special/Order Compliance | 9/17/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Insulation | 10/13/2021 | Partial Approval | CALEB MEISTER |
| Deputy Wood Construction | 10/18/2021 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2021 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 10/21/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/22/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/22/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/27/2021 | Conditional Approval | ARAM AVEDISIAN |
| Green Building Rough | 10/27/2021 | Conditional Approval | ARAM AVEDISIAN |
| MERV13>=Rough | 10/27/2021 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 10/27/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/4/2021 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 11/4/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 11/15/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 11/23/2021 | Conditional Approval | MATT KELLERMAN |
| Gas Test | 11/23/2021 | Conditional Approval | MATT KELLERMAN |
| Interior/Exterior Lathing | 12/9/2021 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/22/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/22/2021 | Approved | ARAM AVEDISIAN |
| Final | 6/22/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 6/22/2022 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Final | 6/22/2022 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/22/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 6/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/29/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/29/2022 | Approved | CHRISTOPHE COCHRAN |