13172 W ORTLEY PL 91401
Certificate Information: 13172 W ORTLEY PL 91401
- Application / Permit
- 20010-20000-05108
- Plan Check / Job No.
- B20VN16730
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACESSORY DWELLING UNIT PER LAMC 12.22A.33(c)&(d)
- Permit Issued
- Issued on 9/24/2021
- Issuing Office
- Current Status
- CofO Issued on 9/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | CHON CHIO KUO |
| Corrections Issued | 1/19/2021 | CHON CHIO KUO |
| Quality Review Completed | 1/29/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/2/2021 | APPLICANT |
| Plan Check Approved | 9/23/2021 | SELLA BENYAMIN |
| Issued | 9/24/2021 | APPLICANT |
| CofO in Progress | 8/22/2022 | RAFAEL CORTES |
| Permit Finaled | 9/6/2022 | MICHAEL SMITH |
| CofO Issued | 9/6/2022 | MICHAEL SMITH |
| Permit Finaled | 9/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/4/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/13/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ADRIAN CASTRO |
| Address approval | Cleared | 5/19/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/18/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 9/23/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 9/23/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/13/2021 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 12/20/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/14/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 2/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Rough | 2/14/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 2/14/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 2/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 2/14/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 2/22/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/28/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 3/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 3/16/2022 | Approved | DAVID MATSON |
| Drywall Nailing | 3/17/2022 | Approved | KRISTEN CAUSEY |
| Gas Test | 4/25/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 6/14/2022 | Corrections Issued | RAFAEL CORTES |
| PLUMBING-Final | 6/14/2022 | Corrections Issued | RAFAEL CORTES |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | MATT KELLERMAN |
| Final | 6/15/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 6/15/2022 | Not Ready for Inspection | MATT KELLERMAN |
| HVAC-Final | 6/15/2022 | Approved | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 6/15/2022 | Corrections Issued | MATT KELLERMAN |
| Smoke Detectors | 6/15/2022 | Approved | MATT KELLERMAN |
| Final | 7/23/2022 | Corrections Issued | COREY HUPP |
| Green Building Final | 7/23/2022 | Not Ready for Inspection | COREY HUPP |
| Service/Power Release | 7/23/2022 | Not Ready for Inspection | COREY HUPP |
| Final | 8/5/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 8/5/2022 | Approved | RAFAEL CORTES |
| Service/Power Release | 8/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 8/22/2022 | OK to Issue CofO | RAFAEL CORTES |
| Service/Power Release | 8/22/2022 | Approved | RAFAEL CORTES |