14637 W PLUMMER ST 91402
Certificate Information: 14637 W PLUMMER ST 91402
- Application / Permit
- 20010-20000-05107
- Plan Check / Job No.
- B20VN16723
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 70' X 131'-2" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; ATTACHED PORCH; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- CofO Issued on 5/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | SELLA BENYAMIN |
| Corrections Issued | 1/7/2021 | SELLA BENYAMIN |
| Quality Review Completed | 1/13/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/13/2021 | APPLICANT |
| Applicant returned to address corrections | 9/14/2021 | SELLA BENYAMIN |
| Applicant returned to address corrections | 10/18/2021 | SELLA BENYAMIN |
| Applicant returned to address corrections | 11/2/2021 | SELLA BENYAMIN |
| Plan Check Approved | 11/12/2021 | SELLA BENYAMIN |
| Issued | 12/10/2021 | APPLICANT |
| CofO in Progress | 4/24/2023 | JENNIFER RABUCHIN |
| CofO Issued | 5/3/2023 | MICHAEL SMITH |
| Permit Finaled | 5/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/23/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/16/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Permit | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/26/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Reinf. Concrete | 2/15/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/15/2022 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 4/12/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 4/12/2022 | Approved | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/15/2022 | Partial Approval | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 4/20/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 4/20/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/13/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/13/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 5/23/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 6/3/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 6/15/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/15/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 6/15/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 9/7/2022 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 9/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 4/17/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/17/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 4/17/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 4/21/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Gas Test | 4/21/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/21/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/21/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 4/21/2023 | Approved | JENNIFER RABUCHIN |