NEW 42'-4" X 20'-6" 1-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2. NFPA 13R FIRE SPRINKLERS REQUIRED THROUGHOUT PER LAFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 ALYSSA N NARCISO
Corrections Issued 1/6/2021 ALYSSA N NARCISO
Quality Review Completed 1/13/2021 STEVEN KIM
Building Plans Picked Up 1/14/2021 APPLICANT
Applicant returned to address corrections 8/16/2021 COLIN LOREDO
Applicant returned to address corrections 9/14/2021 COLIN LOREDO
Plan Check Approved 9/27/2021 COLIN LOREDO
Issued 9/27/2021 APPLICANT
CofO in Progress 12/12/2022 SEAN HAUPT
CofO Issued 1/11/2023 JOHN JANSON
Permit Finaled 1/11/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/7/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/8/2021 GUILLERMO PETRA
Hydrant and Access approval Cleared 3/5/2021 KURT CORRAL
Low Impact Development Cleared 6/3/2021 SUNG JOON WON
Certificate of Compliance Cleared 8/19/2021 MARC WOERSCHING
Miscellaneous Cleared 8/27/2021 NELSON RODRIGUEZ
Private street Cleared 8/27/2021 NELSON RODRIGUEZ
Sewer availability Cleared 9/14/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/15/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/3/2021 Approved SEAN HAUPT
Footing/Foundation/Slab 11/17/2021 Approved SEAN HAUPT
Deputy Steel/Welding 11/22/2021 Approved SEAN HAUPT
BUILDING-Rough-Frame 12/15/2021 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Not Ready for Inspection SEAN HAUPT
Green Building Rough 12/15/2021 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 12/15/2021 Not Ready for Inspection SEAN HAUPT
Deputy Steel/Welding 12/16/2021 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Approved SEAN HAUPT
HVAC-Rough 3/2/2022 Approved SEAN HAUPT
PLUMBING-Rough 3/2/2022 Approved SEAN HAUPT
Structural Steel Frame 3/2/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/3/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 3/3/2022 Approved SEAN HAUPT
Green Building Rough 3/3/2022 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 3/3/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 3/8/2022 Approved SEAN WIRCH
Green Building Rough 3/16/2022 Approved SEAN HAUPT
Insulation 3/16/2022 Approved SEAN HAUPT
Drywall Nailing 3/18/2022 Approved SEAN HAUPT
Shower Pan 3/18/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 4/1/2022 Approved MORRIS JACKSON
ELECTRICAL-Final 10/21/2022 Approved SEAN HAUPT
Final 10/21/2022 Corrections Issued SEAN HAUPT
Gas Test 10/21/2022 Approved SEAN HAUPT
Green Building Final 10/21/2022 Approved SEAN HAUPT
HVAC-Final 10/21/2022 Approved SEAN HAUPT
PLUMBING-Final 10/21/2022 Approved SEAN HAUPT
Service/Power Release 10/21/2022 Not Ready for Inspection SEAN HAUPT
Service/Power Release 11/21/2022 Approved SEAN WIRCH
Final 12/13/2022 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Approved SEAN HAUPT
Smoke Detectors 12/13/2022 Approved SEAN HAUPT