17423 W MAGNOLIA BLVD 91316
Certificate Information: 17423 W MAGNOLIA BLVD 91316
- Application / Permit
- 20010-20000-05070
- Plan Check / Job No.
- B20VN16650
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-4" X 20'-6" 1-STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2. NFPA 13R FIRE SPRINKLERS REQUIRED THROUGHOUT PER LAFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 1/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | ALYSSA N NARCISO |
| Corrections Issued | 1/6/2021 | ALYSSA N NARCISO |
| Quality Review Completed | 1/13/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| Applicant returned to address corrections | 8/16/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 9/14/2021 | COLIN LOREDO |
| Plan Check Approved | 9/27/2021 | COLIN LOREDO |
| Issued | 9/27/2021 | APPLICANT |
| CofO in Progress | 12/12/2022 | SEAN HAUPT |
| CofO Issued | 1/11/2023 | JOHN JANSON |
| Permit Finaled | 1/11/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2021 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/5/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 6/3/2021 | SUNG JOON WON |
| Certificate of Compliance | Cleared | 8/19/2021 | MARC WOERSCHING |
| Miscellaneous | Cleared | 8/27/2021 | NELSON RODRIGUEZ |
| Private street | Cleared | 8/27/2021 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 9/14/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 9/15/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/3/2021 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 11/17/2021 | Approved | SEAN HAUPT |
| Deputy Steel/Welding | 11/22/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/15/2021 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 12/15/2021 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 12/15/2021 | Not Ready for Inspection | SEAN HAUPT |
| Deputy Steel/Welding | 12/16/2021 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | SEAN HAUPT |
| HVAC-Rough | 3/2/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/2/2022 | Approved | SEAN HAUPT |
| Structural Steel Frame | 3/2/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/3/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 3/3/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 3/3/2022 | Not Ready for Inspection | SEAN HAUPT |
| Verify Sprinkler Sign Off | 3/3/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/8/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 3/16/2022 | Approved | SEAN HAUPT |
| Insulation | 3/16/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/18/2022 | Approved | SEAN HAUPT |
| Shower Pan | 3/18/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/1/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 10/21/2022 | Approved | SEAN HAUPT |
| Final | 10/21/2022 | Corrections Issued | SEAN HAUPT |
| Gas Test | 10/21/2022 | Approved | SEAN HAUPT |
| Green Building Final | 10/21/2022 | Approved | SEAN HAUPT |
| HVAC-Final | 10/21/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 10/21/2022 | Approved | SEAN HAUPT |
| Service/Power Release | 10/21/2022 | Not Ready for Inspection | SEAN HAUPT |
| Service/Power Release | 11/21/2022 | Approved | SEAN WIRCH |
| Final | 12/13/2022 | OK to Issue CofO | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/13/2022 | Approved | SEAN HAUPT |