19347 W KITTRIDGE ST 91335

Certificate Information: 19347 W KITTRIDGE ST 91335

Application / Permit
20010-20000-05062
Plan Check / Job No.
B20VN16638
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18'-6" X 40'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(C) AND (D). ALL WORK PER WFPP. [THE L.I.D. CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR L.I.D. REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY]
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
Issued on 9/23/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/29/2020 APPLICANT
Assigned to Plan Check Engineer 1/12/2021 JENNIFER LEE
Corrections Issued 1/14/2021 JENNIFER LEE
Plan Check Approved 9/21/2021 JENNIFER LEE
Issued 9/23/2021 APPLICANT
Building Plans Picked Up 9/23/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/14/2021 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/26/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 9/21/2021 CARLOS AGUILERA

Contact Information

Contractor Trig Builders Inc; Lic. No.: 1030887-B 6442 COLDWATER CANYON AVE 111      NORTH HOLLYWOOD, CA 91606

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2022 Corrections Issued VINCENT HANLEY
Sewer 4/8/2022 Approved VINCENT HANLEY
Underground Mechanical 4/8/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 5/25/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/25/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/14/2022 Approved JEFFREY BULL
Green Building Rough 7/14/2022 Approved JEFFREY BULL
Verify Sprinkler Sign Off 7/14/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 8/4/2022 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved JEFFREY BULL
HVAC-Rough 8/4/2022 Approved JEFFREY BULL
PLUMBING-Rough 8/4/2022 Approved JEFFREY BULL
Insulation 8/10/2022 Conditional Approval JEFFREY BULL
Interior/Exterior Lathing 8/10/2022 Not Ready for Inspection JEFFREY BULL
Shower Pan 8/10/2022 Approved JEFFREY BULL
Drywall Nailing 8/18/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 8/18/2022 Approved JEFFREY BULL
Final 10/27/2022 Corrections Issued JEFFREY BULL
Green Building Final 10/27/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved JEFFREY BULL
Service/Power Release 10/27/2022 Not Required JEFFREY BULL
Smoke Detectors 10/27/2022 Approved JEFFREY BULL
Final 1/4/2023 Not Ready for Inspection JEFFREY BULL
Green Building Final 1/4/2023 Approved JEFFREY BULL