6439 N LONGRIDGE AVE 91401

Certificate Information: 6439 N LONGRIDGE AVE 91401

Application / Permit
20010-20000-05036
Plan Check / Job No.
B20VN16542
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 28'6" X 44'8" ONE STORY DETACHED ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33.(C) AND (E) . ALL WORK PER WFPP “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 10/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 RARES BODEA
Corrections Issued 1/21/2021 RARES BODEA
Building Plans Picked Up 1/22/2021 APPLICANT
Plan Check Approved 2/18/2022 RARES BODEA
Issued 2/18/2022 APPLICANT
CofO in Progress 10/26/2022 MISAEL ESPARZA
Permit Finaled 10/29/2022 MICHAEL SMITH
CofO Issued 10/29/2022 MICHAEL SMITH
Permit Finaled 10/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/27/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/28/2021 GABRIEL ROBLES
Sewer availability Cleared 4/28/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 1/7/2022 ROBERT DUFF
Roof/Waste drainage to street Cleared 1/27/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 2/16/2022 WALTER RAMIREZ
Hold Cleared 2/25/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/23/2022 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 2/28/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/13/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 4/13/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 4/13/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 4/13/2022 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/15/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 4/15/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 4/15/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 4/15/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 4/15/2022 Approved CHRISTOPHE COCHRAN
Insulation 4/20/2022 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 4/20/2022 Approved ASHLEY THOMPSON
Drywall Nailing 4/21/2022 Approved ASHLEY THOMPSON
Sewer 6/1/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 6/1/2022 Approved CHRISTOPHE COCHRAN
Final 10/3/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Final 10/3/2022 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Not Ready RAFAEL CORTES
Service/Power Release 10/3/2022 Not Ready for Inspection RAFAEL CORTES
Smoke Detectors 10/3/2022 Not Ready for Inspection RAFAEL CORTES
Final 10/11/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Final 10/11/2022 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Approved RAFAEL CORTES
Service/Power Release 10/11/2022 Not Ready for Inspection RAFAEL CORTES
Smoke Detectors 10/11/2022 Approved RAFAEL CORTES
Final 10/19/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Service/Power Release 10/19/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 10/25/2022 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 10/25/2022 Approved MISAEL ESPARZA