12746 W LANDALE ST 91604
Certificate Information: 12746 W LANDALE ST 91604
- Application / Permit
- 20010-20000-05022
- Plan Check / Job No.
- B20VN16515
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 103'1" X 38' 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 6/16/2021
- Issuing Office
- Current Status
- CofO Issued on 8/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2021 | RARES BODEA |
| Corrections Issued | 1/9/2021 | RARES BODEA |
| Quality Review Completed | 1/13/2021 | STEVEN KIM |
| Building Plans Picked Up | 1/15/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2021 | RARES BODEA |
| Applicant returned to address corrections | 6/9/2021 | RARES BODEA |
| Plan Check Approved | 6/16/2021 | RARES BODEA |
| Issued | 6/16/2021 | APPLICANT |
| CofO in Progress | 8/19/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
| CofO Issued | 8/24/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/24/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 1/20/2021 | PABLO ESTRADA |
| Address approval | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Permit | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 2/4/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 3/8/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 5/14/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 5/17/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Halo Construction And Development Inc; Lic. No.: 633650-B | 14807 AETNA ST #B VAN NUYS, CA 91411 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/20/2021 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 8/3/2021 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 9/24/2021 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 10/27/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 12/6/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/6/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/10/2021 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/10/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/10/2021 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 12/10/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 1/18/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/18/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 1/21/2022 | Conditional Approval | ARAM AVEDISIAN |
| Drywall Nailing | 2/1/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 2/1/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 3/3/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 3/14/2022 | Partial Approval | ARAM AVEDISIAN |
| Final | 6/3/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/3/2022 | Approved | ARAM AVEDISIAN |
| Final | 6/13/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 6/13/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 6/13/2022 | Approved | ARAM AVEDISIAN |
| Final | 6/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/30/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 7/14/2022 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Service/Power Release | 7/14/2022 | No Access for Inspection | CHRISTOPHE COCHRAN |
| Final | 8/8/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/8/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 8/12/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/12/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 8/19/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 8/19/2022 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/19/2022 | Approved | CHRISTOPHE COCHRAN |