738 N HARPER AVE 90046
Certificate Information: 738 N HARPER AVE 90046
- Application / Permit
- 20010-20000-05018
- Plan Check / Job No.
- B20VN16510
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW IRREGULAR SHAPED (93'-5" X 38', 5,646 SQ. FT) 2-STORY SINGLE FAMILY DWELLING W/ATT GARAGE & ROOF TOP DECK. NFPA 13D SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/13/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | COLIN LOREDO |
| Corrections Issued | 1/7/2021 | COLIN LOREDO |
| Quality Review Completed | 1/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Plan Check Approved | 5/6/2021 | COLIN LOREDO |
| Issued | 5/13/2021 | APPLICANT |
| CofO in Progress | 4/5/2022 | ADAM ESCOTO |
| Permit Finaled | 4/5/2022 | RONALD MYRICK |
| CofO Issued | 4/5/2022 | RONALD MYRICK |
| Permit Finaled | 4/5/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | WALLIE JONG |
| Permit | Cleared | 1/27/2021 | WALLIE JONG |
| Sewer availability | Cleared | 1/27/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2021 | WALLIE JONG |
| Trees in Parkway | Cleared | 2/1/2021 | JOHN KIM |
| Hydrant and Access approval | Cleared | 2/4/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 4/20/2021 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 5/5/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/26/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/2/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/9/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 8/24/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 8/26/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/27/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/31/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/17/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/17/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/23/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/23/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/1/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/21/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 3/21/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 3/21/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 3/23/2022 | Approved | CRAIG DAVIS |
| Green Building Final | 3/23/2022 | Approved | CRAIG DAVIS |
| HVAC-Final | 3/23/2022 | Approved | CRAIG DAVIS |
| Gas Test | 3/25/2022 | Corrections Issued | JOSEPH MCGARRY |
| Final | 4/4/2022 | OK to Issue CofO | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | ADAM ESCOTO |
| Service/Power Release | 4/4/2022 | Approved | ADAM ESCOTO |
| Smoke Detectors | 4/4/2022 | Approved | ADAM ESCOTO |