11729 N PRIMROSE CT 91326

Certificate Information: 11729 N PRIMROSE CT 91326

Application / Permit
20010-20000-05001
Plan Check / Job No.
B20VN16492
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD W/ ATTACHED GARAGE PER STD PLAN #653 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/9/2021
Issuing Office
Current Status
CofO Issued on 7/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2020 APPLICANT
Assigned to Plan Check Engineer 1/21/2021 NILOOFAR MEHRAIN
Corrections Issued 1/26/2021 NILOOFAR MEHRAIN
Quality Review Completed 1/26/2021 CHON CHIO KUO
Building Plans Picked Up 1/26/2021 APPLICANT
Applicant returned to address corrections 8/3/2021 PETER MOSESIAN
Plan Check Approved 8/6/2021 PETER MOSESIAN
Issued 8/9/2021 APPLICANT
CofO in Progress 7/12/2022 SEAN WIRCH
Permit Finaled 7/14/2022 MICHAEL SMITH
CofO Issued 7/14/2022 MICHAEL SMITH
Permit Finaled 7/14/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 6/9/2021 AMMAR ELTAWIL
Address approval Cleared 6/15/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 6/15/2021 LEE GUILBEAUX
Permit Cleared 6/15/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/15/2021 LEE GUILBEAUX
Sewer availability Cleared 6/15/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/15/2021 LEE GUILBEAUX
"T" removal Cleared 6/16/2021 DANG NGUYEN
Miscellaneous Cleared 6/16/2021 DANG NGUYEN
Miscellaneous Cleared 6/16/2021 DANG NGUYEN
Miscellaneous Cleared 6/16/2021 DANG NGUYEN
Miscellaneous Cleared 6/16/2021 DANG NGUYEN
Specific Plan Cleared 6/16/2021 DANG NGUYEN
Tract Map conditions Cleared 6/16/2021 DANG NGUYEN
ZA Case Cleared 6/16/2021 DANG NGUYEN
ZA Case Cleared 6/16/2021 DANG NGUYEN
ZI Cleared 6/16/2021 DANG NGUYEN
Hydrant and Access approval Cleared 6/29/2021 ROBERT DUFF
GPI Written Notices Cleared 8/6/2021 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 8/6/2021 NILOOFAR MEHRAIN

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 1140 VIRGINIA DR ATTN: TOLL   BROTHERS - TAGGERT/LEGAL    FORT WASHINGTON, PA 19034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Pre-Stress Concrete 10/19/2021 No Access for Inspection SEAN WIRCH
Underground Mechanical 11/15/2021 Approved SEAN WIRCH
Footing/Foundation/Slab 12/7/2021 Approved SEAN WIRCH
Deputy Reinf. Concrete 12/9/2021 Approved SEAN WIRCH
Sewer 12/23/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval SEAN WIRCH
Deputy Drilled-In Anchors 3/14/2022 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval SEAN WIRCH
Rough-Elec/Plmb/HVAC 3/15/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 3/17/2022 Not Ready for Inspection SEAN WIRCH
Green Building Rough 3/17/2022 Not Ready for Inspection SEAN WIRCH
Verify Sprinkler Sign Off 3/17/2022 Not Ready for Inspection SEAN WIRCH
Deputy Reinf. Concrete 3/21/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 3/25/2022 Approved SEAN WIRCH
Drywall Nailing 3/29/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 4/5/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Approved SEAN WIRCH
Service/Power Release 5/9/2022 Approved SEAN WIRCH
ELECTRICAL-Final 6/16/2022 Approved SEAN WIRCH
HVAC-Final 6/16/2022 Approved SEAN WIRCH
PLUMBING-Final 6/16/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 7/12/2022 Approved SEAN WIRCH
Final 7/12/2022 OK to Issue CofO SEAN WIRCH
Green Building Final 7/12/2022 Approved SEAN WIRCH
Green Building Rough 7/12/2022 Approved SEAN WIRCH
Smoke Detectors 7/12/2022 Approved SEAN WIRCH
Verify Sprinkler Sign Off 7/12/2022 Approved SEAN WIRCH