11745 N PRIMROSE CT 91326
Certificate Information: 11745 N PRIMROSE CT 91326
- Application / Permit
- 20010-20000-04998
- Plan Check / Job No.
- B20VN16492
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE PER STD PLAN #653 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/26/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/26/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/26/2021 | APPLICANT |
| Applicant returned to address corrections | 8/3/2021 | PETER MOSESIAN |
| Plan Check Approved | 8/6/2021 | PETER MOSESIAN |
| Issued | 8/9/2021 | APPLICANT |
| CofO in Progress | 6/22/2022 | SEAN WIRCH |
| Permit Finaled | 6/22/2022 | MICHAEL SMITH |
| CofO Issued | 6/22/2022 | MICHAEL SMITH |
| Permit Finaled | 6/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/9/2021 | AMMAR ELTAWIL |
| Address approval | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Permit | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/15/2021 | LEE GUILBEAUX |
| "T" removal | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 6/16/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 6/16/2021 | DANG NGUYEN |
| ZA Case | Cleared | 6/16/2021 | DANG NGUYEN |
| ZA Case | Cleared | 6/16/2021 | DANG NGUYEN |
| ZI | Cleared | 6/16/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 6/29/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 8/6/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 8/6/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/1/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 9/23/2021 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 9/24/2021 | Approved | SEAN WIRCH |
| Sewer | 10/14/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Corrections Issued | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 12/22/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 12/22/2021 | Corrections Issued | SEAN WIRCH |
| PLUMBING-Rough | 12/22/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 1/4/2022 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2022 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 1/26/2022 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 1/26/2022 | Approved | SEAN WIRCH |
| Drywall Nailing | 2/4/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 2/4/2022 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 2/16/2022 | Approved | SEAN WIRCH |
| Underground Mechanical | 3/7/2022 | Approved | SEAN WIRCH |
| Gas Test | 3/8/2022 | Approved | SEAN WIRCH |
| Service/Power Release | 3/17/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 5/3/2022 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Approved | SEAN WIRCH |
| HVAC-Final | 6/9/2022 | Approved | SEAN WIRCH |
| PLUMBING-Final | 6/9/2022 | Approved | SEAN WIRCH |
| Final | 6/21/2022 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 6/21/2022 | Approved | SEAN WIRCH |
| Smoke Detectors | 6/21/2022 | Approved | SEAN WIRCH |