11763 N PRIMROSE CT 91326
Certificate Information: 11763 N PRIMROSE CT 91326
- Application / Permit
- 20010-20000-04994
- Plan Check / Job No.
- B20VN16492
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD W/ ATTACHED GARAGE PER STD PLAN #653 (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 8/9/2021
- Issuing Office
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/26/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/26/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 1/26/2021 | APPLICANT |
| Applicant returned to address corrections | 8/3/2021 | PETER MOSESIAN |
| Plan Check Approved | 8/6/2021 | PETER MOSESIAN |
| Issued | 8/9/2021 | APPLICANT |
| CofO in Progress | 7/11/2022 | SEAN WIRCH |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
| CofO Issued | 7/14/2022 | MICHAEL SMITH |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/9/2021 | AMMAR ELTAWIL |
| Address approval | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Permit | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/15/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/15/2021 | LEE GUILBEAUX |
| "T" removal | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 6/16/2021 | DANG NGUYEN |
| Specific Plan | Cleared | 6/16/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 6/16/2021 | DANG NGUYEN |
| ZA Case | Cleared | 6/16/2021 | DANG NGUYEN |
| ZA Case | Cleared | 6/16/2021 | DANG NGUYEN |
| ZI | Cleared | 6/16/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 6/29/2021 | ROBERT DUFF |
| GPI Written Notices | Cleared | 7/27/2021 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 7/27/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/15/2021 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 12/7/2021 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 12/9/2021 | Approved | SEAN WIRCH |
| Sewer | 12/23/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2022 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Rough | 2/28/2022 | Approved | SEAN WIRCH |
| HVAC-Rough | 2/28/2022 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 2/28/2022 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 3/1/2022 | Approved | SEAN WIRCH |
| Green Building Rough | 3/1/2022 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 3/1/2022 | Approved | SEAN WIRCH |
| Drywall Nailing | 3/14/2022 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 3/14/2022 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 3/21/2022 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 4/1/2022 | Approved | SEAN WIRCH |
| Gas Test | 4/6/2022 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 5/2/2022 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Approved | SEAN WIRCH |
| Underground Mechanical | 5/19/2022 | Approved | SEAN WIRCH |
| HVAC-Final | 6/23/2022 | Approved | SEAN WIRCH |
| PLUMBING-Final | 6/23/2022 | Approved | SEAN WIRCH |
| Final | 7/11/2022 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 7/11/2022 | Approved | SEAN WIRCH |
| Service/Power Release | 7/11/2022 | Approved | SEAN WIRCH |
| Smoke Detectors | 7/11/2022 | Approved | SEAN WIRCH |