2652 1/2 S ELLENDALE PL 90007
Certificate Information: 2652 1/2 S ELLENDALE PL 90007
- Application / Permit
- 20010-20000-04939
- Plan Check / Job No.
- B20VN16472
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 44'4" X 33' DETACHED 2-STORY ACCESSORY DWELLING UNIT AS PER GCS 65852.2(E)(1)(D) AND LAMC 12.22 A.33(c)¹, (d)¹, and (g) W/GROUND FLOOR 8 CAR GARAGE, NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING; “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.” - SEE COMMENTS
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofO Issued on 8/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2021 | RARES BODEA |
| Corrections Issued | 2/7/2021 | RARES BODEA |
| Quality Review Completed | 2/11/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/11/2021 | APPLICANT |
| Applicant returned to address corrections | 8/10/2021 | RARES BODEA |
| Applicant returned to address corrections | 10/6/2021 | RARES BODEA |
| Plan Check Approved | 10/7/2021 | RARES BODEA |
| Issued | 3/9/2022 | APPLICANT |
| CofO in Progress | 7/27/2023 | KATHRYN BUTTERWORTH |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
| CofO Issued | 8/13/2023 | DEROLD HAUFF |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2021 | JEANIE LAM |
| Construction near power lines | Cleared | 3/23/2021 | RIDWAN HARDY |
| Sewer availability | Cleared | 5/14/2021 | JEANIE LAM |
| HPOZ | Cleared | 8/18/2021 | DANIEL MATA |
| Specific Plan | Cleared | 8/18/2021 | DANIEL MATA |
| ZI | Cleared | 8/18/2021 | DANIEL MATA |
| ZA Case | Cleared | 8/24/2021 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 8/25/2021 | KURT CORRAL |
| Miscellaneous | Cleared | 8/27/2021 | KENTON TRINH |
| ZA Case | Cleared | 8/27/2021 | KENTON TRINH |
| ZI | Cleared | 8/30/2021 | KENTON TRINH |
| Roof/Waste drainage to street | Cleared | 9/28/2021 | JEANIE LAM |
Contact Information
| Architect | Badie,, Amin; Lic. No.: C28846 | 4386 BECK AVENUE STUDIO CITY, CA 91604 |
| Contractor | Hillstar Construction Inc; Lic. No.: 972213-B | 22647 VENTURA BLVD #173 WOODLAND HILLS, CA 91364 |
| Engineer | Funk,, David Lyle; Lic. No.: S5421 | 319 MAIN STREET EL SEGUNDO, CA 90245 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/17/2022 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/28/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 4/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 4/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 5/2/2022 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 5/9/2022 | Approved | KATHRYN BUTTERWORTH |
| Deputy Other (see comments) | 5/16/2022 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/16/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 5/16/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 5/16/2022 | Approved | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 5/19/2022 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 6/28/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 6/29/2022 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 7/5/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 8/1/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 8/18/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 9/9/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 9/26/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 10/24/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 10/25/2022 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 10/25/2022 | Approved | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 10/25/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 10/25/2022 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 11/3/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Rough-Elec/Plmb/HVAC | 11/3/2022 | Approved | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 11/10/2022 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 11/15/2022 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/15/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 11/28/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 11/28/2022 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 12/1/2022 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/25/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Gas Test | 2/13/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 2/23/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 3/31/2023 | Approved | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/3/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/17/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 5/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 5/3/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 5/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 5/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 5/3/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 5/8/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Gas Test | 5/8/2023 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 5/8/2023 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 5/8/2023 | Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 5/8/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Final | 6/23/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 6/23/2023 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 6/23/2023 | Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 6/23/2023 | Approved | KATHRYN BUTTERWORTH |
| Final | 7/26/2023 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Structural Steel Frame | 7/26/2023 | Approved | KATHRYN BUTTERWORTH |