3950 S DENKER AVE 90062

Certificate Information: 3950 S DENKER AVE 90062

Application / Permit
20010-20000-04919
Plan Check / Job No.
B20VN16395
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 19' X 19' DETACHED GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 RAPHAEL ROSAS
Corrections Issued 12/31/2020 RAPHAEL ROSAS
Plan Check Approved 10/12/2021 JENNIFER LEE
Issued 10/13/2021 APPLICANT
Building Plans Picked Up 10/20/2021 APPLICANT
CofO in Progress 5/27/2022 RYAN SALAZAR
No Progress 3/14/2023 RICHARD STEINBACH
Permit Finaled 12/4/2024 DEROLD HAUFF
CofO Issued 12/4/2024 DEROLD HAUFF
Permit Finaled 12/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 5/21/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 6/30/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/1/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/11/2022 Corrections Issued JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 2/18/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 2/18/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 5/2/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 5/2/2022 Approved SABAS ALONSO
Pre-Inspection 5/6/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 5/26/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 5/26/2022 Approved RYAN SALAZAR
Final 5/26/2022 OK to Issue CofO RYAN SALAZAR
Green Building Final 5/26/2022 Approved RYAN SALAZAR
Green Building Rough 5/26/2022 Approved RYAN SALAZAR
HVAC-Final 5/26/2022 Approved RYAN SALAZAR
PLUMBING-Final 5/26/2022 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/26/2022 SGSOV Not Required RYAN SALAZAR
Service/Power Release 5/26/2022 Approved RYAN SALAZAR
Smoke Detectors 5/26/2022 Approved RYAN SALAZAR
Special/Order Compliance 6/15/2022 Corrections Issued HORACE FULTZ