11299 N ADELPHIA AVE 91331

Certificate Information: 11299 N ADELPHIA AVE 91331

Application / Permit
20010-20000-04902
Plan Check / Job No.
B20VN16360
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21' X 36' IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 4/22/2022
Issuing Office
Current Status
CofO in Progress on 9/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/19/2020 APPLICANT
Assigned to Plan Check Engineer 12/30/2020 RAPHAEL ROSAS
Corrections Issued 12/30/2020 RAPHAEL ROSAS
Building Plans Picked Up 1/27/2022 APPLICANT
Plan Check Approved 4/22/2022 RAPHAEL ROSAS
Issued 4/22/2022 APPLICANT
CofO in Progress 9/19/2023 MICHEL ABAJAN
CofO in Progress 10/17/2023 ROBERT GOLD

Permit Application Clearance Information

Construction near power lines Cleared 3/31/2021 RIDWAN HARDY
Address approval Cleared 7/6/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/7/2021 GABRIEL ROBLES
Sewer availability Cleared 7/7/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 10/3/2021 KURT CORRAL
Grading Pre-Inspection Cleared 11/1/2021 BRIAN MILLER
Low Impact Development Cleared 11/30/2021 TA ANH
Roof/Waste drainage to street Cleared 2/28/2022 JOHN LIN
GPI Written Notices Cleared 4/12/2022 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/17/2022 Corrections Issued MICHEL ABAJAN
Underground Mechanical 5/18/2022 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 6/6/2022 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/9/2022 Approved JENNIFER RABUCHIN
Sewer 6/21/2022 Approved MICHEL ABAJAN
Underground Mechanical 6/21/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 7/8/2022 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 7/8/2022 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 7/8/2022 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 7/8/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 7/8/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/12/2022 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Partial Approval MICHEL ABAJAN
Green Building Rough 7/12/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 7/12/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/15/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 7/15/2022 Approved MICHEL ABAJAN
Green Building Rough 7/15/2022 Approved MICHEL ABAJAN
HVAC-Rough 8/10/2022 Approved MICHEL ABAJAN
Insulation 8/10/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 8/10/2022 Approved MICHEL ABAJAN
Drywall Nailing 9/9/2022 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/7/2023 Approved MICHEL ABAJAN
PLUMBING-Final 2/7/2023 Approved MICHEL ABAJAN
Final 2/14/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 2/14/2023 Approved MICHEL ABAJAN
HVAC-Final 2/14/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 2/14/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 2/14/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 9/19/2023 Approved MICHEL ABAJAN
Final 9/19/2023 Conditional Approval MICHEL ABAJAN
HVAC-Final 9/19/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/19/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 9/19/2023 Approved MICHEL ABAJAN
Smoke Detectors 9/19/2023 Approved MICHEL ABAJAN
Pre-Inspection 10/18/2023 Corrections Issued MICHEL ABAJAN