534 3/4 W VERNON AVE 90037

Certificate Information: 534 3/4 W VERNON AVE 90037

Application / Permit
20010-20000-04882
Plan Check / Job No.
B20VN16294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (10'-0"x 31'-7") IRR SHAPE DETACHED ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d) WITH 13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 1/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2021 TROY DEGUZMAN
Corrections Issued 1/10/2021 TROY DEGUZMAN
Quality Review Completed 1/12/2021 CHON CHIO KUO
Building Plans Picked Up 1/13/2021 APPLICANT
Applicant returned to address corrections 9/28/2021 TROY DEGUZMAN
Applicant returned to address corrections 11/15/2021 TROY DEGUZMAN
Applicant returned to address corrections 11/19/2021 TROY DEGUZMAN
Plan Check Approved 12/2/2021 TROY DEGUZMAN
Issued 12/2/2021 APPLICANT
CofO in Progress 1/10/2023 ALEJANDRO DE ARTOLA
Permit Finaled 1/14/2023 DEROLD HAUFF
CofO Issued 1/14/2023 DEROLD HAUFF
Permit Finaled 1/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/20/2021 MATTHEW CRAIG
Low Impact Development Cleared 7/22/2021 JORGE MEJIA LEMUS
Address approval Cleared 7/28/2021 RENZ SORIANO
Sewer availability Cleared 8/2/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/9/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/9/2021 RENZ SORIANO
Highway dedication Cleared 9/16/2021 RENZ SORIANO
Green Code Cleared 9/28/2021 TROY DEGUZMAN

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 14263 VALLEY VISTA BLVD.      SHERMAN OAKS, CA 91403
Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/17/2021 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 12/17/2021 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/21/2021 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/21/2021 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 1/12/2022 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 2/17/2022 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/4/2022 Not Ready for Inspection JOAQUIN GREENOUGH
ELECTRICAL-Rough 4/4/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 4/4/2022 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 4/4/2022 Not Ready for Inspection JOAQUIN GREENOUGH
MERV13>=Rough 4/4/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 4/4/2022 Corrections Issued JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 4/4/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/6/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 4/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
MERV13>=Rough 4/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 4/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Drywall Nailing 4/27/2022 Approved HORACE FULTZ
Green Building Rough 4/27/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 4/27/2022 Approved HORACE FULTZ
Gas Test 6/16/2022 Approved JOAQUIN GREENOUGH
Sewer 6/16/2022 Approved JOAQUIN GREENOUGH
Verify Rec and Parks Fee Memo 6/16/2022 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 9/13/2022 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 9/13/2022 Approved ALEJANDRO DE ARTOLA
Gas Test 11/16/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/18/2022 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/19/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/19/2022 Approved ALEJANDRO DE ARTOLA
Final 12/19/2022 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 12/19/2022 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/19/2022 Corrections Issued ALEJANDRO DE ARTOLA
MERV13>=Final 12/19/2022 Approved ALEJANDRO DE ARTOLA
MERV13>=Rough 12/19/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/19/2022 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/19/2022 Approved ALEJANDRO DE ARTOLA
Final 12/23/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/23/2022 Approved ALEJANDRO DE ARTOLA
Final 12/27/2022 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/9/2023 OK to Issue CofO ALEJANDRO DE ARTOLA