4606 N WOODLEY AVE 91436

Certificate Information: 4606 N WOODLEY AVE 91436

Application / Permit
20010-20000-04872
Plan Check / Job No.
B20VN16276
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(B) & LAMC 12.22 A.33(c)(d)(g) (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 3/16/2022
Issuing Office
Current Status
Issued on 3/16/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/18/2020 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 NILOOFAR MEHRAIN
Corrections Issued 1/19/2021 NILOOFAR MEHRAIN
Quality Review Completed 1/19/2021 CHON CHIO KUO
Building Plans Picked Up 1/20/2021 APPLICANT
Applicant returned to address corrections 6/15/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/21/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 12/22/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/3/2022 NILOOFAR MEHRAIN
Plan Check Approved 3/11/2022 NILOOFAR MEHRAIN
Issued 3/16/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/26/2021 LEE GUILBEAUX
Miscellaneous Cleared 4/26/2021 LEE GUILBEAUX
Miscellaneous Cleared 4/26/2021 LEE GUILBEAUX
Permit Cleared 4/26/2021 LEE GUILBEAUX
Tract Map conditions Cleared 4/27/2021 PABLO ESTRADA
ZA Case Cleared 4/27/2021 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 4/28/2021 LEE GUILBEAUX
Sewer availability Cleared 4/28/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/28/2021 LEE GUILBEAUX
Hydrant and Access approval Cleared 6/25/2021 JOHN CONNEALLY
Trees in Parkway Cleared 11/9/2021 ADALBERTO VERA
Low Impact Development Cleared 12/7/2021 TA ANH
Roof/Waste drainage to street Cleared 12/9/2021 JOHN LIN
GPI Written Notices Cleared 1/26/2022 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 1/26/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/24/2022 Partial Approval PETER FOLLING
Underground Mechanical 3/24/2022 Partial Approval PETER FOLLING
Excavation/Setback/Form/Re-Bar 3/25/2022 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 3/25/2022 Corrections Issued DAVID SANDOVAL
Underground Mechanical 4/5/2022 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Corrections Issued VINCENT HANLEY
HVAC-Rough 5/3/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 5/3/2022 Not Ready for Inspection VINCENT HANLEY
Deputy Wood Construction 5/4/2022 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 5/6/2022 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Approved ROBERT GOLD
Footing/Foundation/Slab 5/6/2022 Approved ROBERT GOLD
HVAC-Rough 5/6/2022 Approved ROBERT GOLD
Special/Order Compliance 5/6/2022 Partial Inspection MORRIS JACKSON
BUILDING-Rough-Frame 5/17/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 5/17/2022 Approved DAVID SANDOVAL
Green Building Rough 5/17/2022 Not Ready for Inspection DAVID SANDOVAL
Interior/Exterior Lathing 5/17/2022 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 5/17/2022 Approved DAVID SANDOVAL
Verify Sprinkler Sign Off 5/17/2022 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 5/20/2022 Partial Inspection VINCENT HANLEY
ELECTRICAL-Rough 5/20/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/20/2022 Approved VINCENT HANLEY
Green Building Rough 5/20/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/20/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 5/20/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/20/2022 Approved VINCENT HANLEY
Insulation 5/25/2022 Approved MORRIS JACKSON
Drywall Nailing 6/2/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/2/2022 Approved MORRIS JACKSON
Special/Order Compliance 8/2/2022 Partial Inspection MICHAEL PELHAM
BUILDING-Rough-Frame 11/7/2022 Approved VINCENT HANLEY
Final 11/7/2022 Corrections Issued VINCENT HANLEY
Green Building Final 11/7/2022 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/7/2022 SGSOV Approved VINCENT HANLEY
Service/Power Release 11/7/2022 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 11/7/2022 Approved VINCENT HANLEY
Final 11/30/2022 Not Ready for Inspection SEAN WIRCH
Service/Power Release 11/30/2022 Approved SEAN WIRCH